First decide what kind of inconsistency it is.
• Arithmetic inconsistency in prices: apply the correction rules in the Tender Document (unit rate generally prevails, etc.). This is not a matter for negotiation.
• Inconsistency in non-price information: check whether the Tender Document has an order of precedence among tender documents. If not, consider a written clarification request.
When using clarification:
• Ask a factual question, for example 'Please confirm which model is offered for Item 3'.
• The answer must not change the substance or price. If the clarification would allow the tenderer to choose a more favourable option after seeing others' prices, be cautious, since that could give an unfair advantage.
• If one version is compliant and the other is not, and the inconsistency cannot be resolved without changing the substance, the committee may need to conclude that compliance is not demonstrated.
Record the inconsistency, any clarification and the committee's reasoning. Apply the same approach to all tenders.