Both are RFQ documents for Physical Services up to Tk 1.5 million (Tk 15 lakh), excluding hiring service personnel under the Outsourcing Policy. The difference is how the price is set and paid.
e-PPS1BU (unit rate):
• The tenderer quotes a rate for each unit (per day, per trip, per square metre and so on).
• Payment is rate × quantity actually delivered and measured.
• Suits work where quantities are estimates and may change.
e-PPS1BL (lump sum):
• The tenderer quotes one total price for a clearly defined scope.
• Payment is the fixed price, often in milestones, regardless of the effort used.
• Suits work with a fixed, well-described output, so the tenderer carries the quantity risk.
How to choose: if the PE can describe the full output precisely, lump sum is simpler to manage. If quantities are uncertain, unit rate is fairer and easier to adjust. Record the reason for the choice in the procurement file.