Construction of 44.02m. (42.68m. X 1) Long P.C. Girder Kukua Bazar Bridge over Kukua-Golachipa khal at 80th (P) Km. (Ch. 79+279m.) of Lebukhali-Bauphal-Golachipa-Amragachia Road (Z-8806), Under Patuakhali Road Division During the year 2026-2027.
Construction of 44.02m. (42.68m. X 1) Long P.C. Girder Kukua Bazar Bridge over Kukua-Golachipa khal at 80th (P) Km. (Ch. 79+279m.) of Lebukhali-Bauphal-Golachipa-Amragachia Road (Z-8806), Under Patuakhali Road Division During the year 2026-2027.
Procurement summary
- Procuring entity
- Patuakhali Road Division
- Organization
- roads & highways department (rhd)
- Division
- road transport and highways division
- Ministry
- ministry of road transport and bridges
- Location
- Patuakhali, Patuakhali
- Procurement nature
- Works
- Procurement type
- NCT
- Procurement method
- Open Tendering Method (OTM)
- Lot
- 06/e-GP/PMP-Bridge/PATRHD/2026-2027
Key dates
- Published
- 15 October 2026
- Document last selling date
- 15 November 2026
- Tender security submission deadline
- 16 November 2026
- Closing date
- 16 November 2026
Costs and securities
- Estimated cost (APP)
- BDT 9,49,11,900
- Document price
- BDT 4,000
- Tender security
- BDT 25,00,000
Funding
- Budget type
- Revenue
Eligibility criteria
All tenderers of Bangladeshi National regardless of whether enlisted or not enlisted with the employer may submit Tenders provided that they are qualified as per Qualification Criteria Specified in the Tender Data Sheet (TDS) of the Tender Document. 1. In case of JVCA Experience Certificates (Turnover) submission, the tenderer must submit the documents (Joint Venture Agreement etc) in favour of percent share among all the Joint Venture partners. 2. In case of JV, Lead partner as well as other partner/s shall have the experience separately of similar nature of works as stated in TDS. 3. Tenderer must submit the ownership/Lease/Hire documents of their plants & equipments. 4. For submission of any false information and documents, the Tenderer shall be considererd as Non-Responsive and be De-barred. 5. Tenderer must submit On-going Works and Current Commitment(s) details under all PE's Organization. Hiding On-going Works and Current Commitment(s) will be considered as fraudulent practice…