Tender ID 1366389

Feeder Bifurcation of 11KV Chourongi Feeder under S&D-1, Faridpur.

Feeder Bifurcation of 11KV Chourongi Feeder under S&D-1, Faridpur.

Procurement summary

Procuring entity
Office of the Executive Engineer, Sales and Distribution Division-1, WZPDCL, Faridpur
Organization
west zone power distribution company ltd (wzpdcl)
Division
power division
Ministry
ministry of energy, power and mineral resources
Location
Faridpur, Faridpur
Procurement nature
Works
Procurement type
NCT
Procurement method
Open Tendering Method (OTM)
Lot
FA-01-01/26-27
Package no.
FA-01-01/26-27
APP ID
235325
Invitation reference no.
27.22.2947.401.016.001.26.377; Dated: 12/11/2026

Key dates

Published
12 November 2026
Document last selling date
29 November 2026
Pre-tender meeting
12 November 2026
Tender security submission deadline
29 November 2026
Opening date
29 November 2026
Closing date
29 November 2026

Costs and securities

Estimated cost (APP)
BDT 3,80,000
Document price
BDT 500
Tender security
BDT 9,000

Funding

Budget type
Own Fund
Source of funds
Own Fund

Eligibility criteria

a. 1st class Contractor with Updated ABC licence from electrical license board, Bangladesh b. Updated Trade Licence, vat registration and Income tax certificate. c. Experience of installation and Execution of 33KV, 11KV, 11/0.4 KV line renovation or construction . No Falsified data is allowed. d. Satisfactory genuine work completion certificate of similar work volume of which will be be minimum 1 of contract(s) having minimum Tk 2,00,000(two lac) over a period of last 5 (Five) years shall be required issued from only BPDB, WZPDCL, DESCO, DPDC, NESCO not below the rank of Executive Engineer under whom the work was done. e. Annual audit report from a recognized Chartered Accounted firm f) Average annual volume of construction turn over shall be minimum Tk 2,00,000 . g) Liquid assets/availability of funds and/or credit facilities from bidder's banker(s) at least Tk 2,50,000 . h) Tenderer shall under no circumstances assign the works or any part of it to the subcontractor(s). i) All the P…