River Bank Protection work from km 14.700 to km 14.900 = 0.200 km of Polder no 56/57 in C/W Protection of Shibpur, Dhonia and Madua Area under Bhola sadar and Daulatkhan upazila from Erosion of Meghna River under Bhola WD Division-I, BWDB, Bhola. (DSM-RBP-07)
River Bank Protection work from km 14.700 to km 14.900 = 0.200 km of Polder no 56/57 in C/W Protection of Shibpur, Dhonia and Madua Area under Bhola sadar and Daulatkhan upazila from Erosion of Meghna River under Bhola WD Division-I, BWDB, Bhola. (DSM-RBP-07)
Procurement summary
- Procuring entity
- Bhola WD Division-1
- Organization
- bangladesh water development board (bwdb)
- Ministry
- ministry of water resources
- Location
- Bhola, Bhola
- Procurement nature
- Works
- Procurement type
- NCT
- Procurement method
- Open Tendering Method (OTM)
- Lot
- DSM-RBP-07
- Package no.
- DSM-RBP-07
- APP ID
- 235392
- Invitation reference no.
- T-2/481, Dated:03-11-2026
Key dates
- Published
- 4 November 2026
- Document last selling date
- 26 November 2026
- Pre-tender meeting
- 5 November 2026
- Tender security submission deadline
- 26 November 2026
- Opening date
- 26 November 2026
- Closing date
- 26 November 2026
Costs and securities
- Estimated cost (APP)
- BDT 23,89,06,012
- Document price
- BDT 5,000
- Tender security
- BDT 55,00,000
Funding
- Project
- Protection of Shibpur, Dhonia and Madua Area under Bhola Sadar and Daulatkhan Upazila from Erosion of the Meghna River
- Budget type
- Development
- Source of funds
- Government
Eligibility criteria
1) Tenderer must be registered in the e-GP portal through CPTU along with valid and updated Trade License, VAT Registration and TIN certificate. 2) Payment shall be made subject to availability of fund. 3) All Non-life insurance for any public property, or risks or liabilities pertaining to public property, shall be taken through Sadharon Bima Corporation in accordance with the Insurance Corporation Act, 2019. 4) It is the duty of contractor to submit all the documents freshly (without corrupted). If any documents get corrupted and evaluation committee could not be able to open the file, no claim from the tenderer will be entertained regarding the file. 5) A detailed list of work in hand/on-going works duly signed by the tenderer must be submitted. 6) If any kind of obstacles/structures is needed to dismantle to execute the work as per design and specification the tenderer will do this at his/her own arrangement and cost. No extra claim will be entertained in this regard. 7) If BWDB o…