Single Bituminous Surface Treatment (SBST) work at Ch. 11+350 to 11+380 km, Ch. 21+550 to 22+646 km, 23+910 to 24+004 L/S km of Jamalpur- Sherpur- Bongaon (R- 460) road under Sherpur Road Division During the year-2026-2027.
Single Bituminous Surface Treatment (SBST) work at Ch. 11+350 to 11+380 km, Ch. 21+550 to 22+646 km, 23+910 to 24+004 L/S km of Jamalpur- Sherpur- Bongaon (R- 460) road under Sherpur Road Division During the year-2026-2027.
Procurement summary
- Procuring entity
- Sherpur Road Division
- Organization
- roads & highways department (rhd)
- Division
- road transport and highways division
- Ministry
- ministry of road transport and bridges
- Location
- Sherpur, Sherpur
- Procurement nature
- Works
- Procurement type
- NCT
- Procurement method
- Open Tendering Method (OTM)
- Lot
- e-GP/Rev-26/OTM/SherD/26-27
- Package no.
- e-GP/Rev-26/OTM/SherD/26-27
- APP ID
- 227255
- Invitation reference no.
- e-GP/Rev-26/OTM/SherD/26-27
Key dates
- Published
- 15 November 2026
- Document last selling date
- 29 November 2026
- Pre-tender meeting
- 15 November 2026
- Tender security submission deadline
- 29 November 2026
- Opening date
- 29 November 2026
- Closing date
- 29 November 2026
Costs and securities
- Estimated cost (APP)
- BDT 36,37,000
- Document price
- BDT 1,500
- Tender security
- BDT 95,000
Funding
- Budget type
- Revenue
- Source of funds
- Government
Eligibility criteria
All / Any Bangladeshi national tenderers regardless of whether enlisted or not enlisted with the employer may submit Tenders provided that they are qualified as per Qualification Criteria Specified in the Tender Data Sheet (TDS) of the Tender Document. The following conditions shall be considered: 1. The Tenders shall be evaluated in the e-GP system with the help of necessary database (If Required). 2. Tenderers are requested to submit only necessary documents to qualify for eligibility criteria. They are discouraged to submit unnecessary additional documents. 3. If any dissimilarity found in documents submitted by tenderers at any stage of evaluation process, the tenderers will be considered non-Responsive. 4. Any non submission of ongoing work or any other information that affect the tender evaluation will be considered as non-eligibility of the tenderer. 5. The tenderers will have to submit year wise payment list . 6. The tenderers will have to submit list of ongoing works of RHD/o…