e-PG2 · Goods OTM / LTM · For Bidders

e-PG2 Goods Tender Participation Guideline

How to qualify for, price and submit a responsive goods tender up to Tk. 50 lakh under the Open or Limited Tendering Method in e-GP, and what follows from opening through award, delivery, payment and warranty.

Based on e-PG2, October 2025 · Last reviewed 11 October 2026

Submission Checklist Find Live Tenders

Preparing the tender as a Procuring Entity? Read the e-PG2 preparation guideline.

At a glance

  • Buy the document in e-GP through a member bank, up to the day before the deadline.
  • Missing forms, priced schedule or tender security means instant rejection.
  • More than 10% above the estimate, or below the SLT limit, is rejected.
  • Win: 10% performance security in 7 working days, sign within 14 days.
  • No subcontracting; 10% retention held until warranty ends.

For suppliers, traders and manufacturers with an active e-GP registration (and, for LTM, valid enlistment with the PE).

A non-responsive tender cannot be fixed later. Material deviations, reservations or omissions found at evaluation cannot be corrected afterwards. Read the TDS and PCC attached in e-GP; they set the numbers for your package and take priority over this guide.

On this page

Before you tender

01Is This Tender for You? 02Eligibility 03Qualification Criteria 04Questions and Addenda

Build the tender

05Documents to Upload 06Tender Security 07Price Your Tender 08Technical Compliance 09Submit Through e-GP

After you submit

10How You Are Evaluated 11Award and Contract Signing 12Delivery, Payment and Warranty 13Delays, Penalties and Disputes 14Submission Checklist

01Is This Tender for You?

e-PG2 is BPPA's Standard e-Tender Document for national goods tenders up to Tk. 50 lakh under OTM or LTM. You will see "e-PG2" as the STD in the e-GP notice.

Nature
Goods and related services
Value
Up to Tk. 50 lakh
Method
OTM (open) or LTM (enlisted)
Currency
Bangladesh Taka, fixed price
Performance security
10% of contract price
Award to
Lowest evaluated responsive

Under LTM, you must hold updated, valid enlistment with the Procuring Entity, and the TDS says whether tender security is needed.

02Eligibility

  • Legal capacity to sign the contract, and enrolment in the relevant professional or trade organisation in your country.
  • Taxes and social security contributions paid as required by law.
  • Not under suspension or debarment for corrupt, fraudulent, collusive, coercive or obstructive practices, or for fundamental breach of contract, and not restricted by any development partner in Bangladesh.
  • Not insolvent, in receivership, bankrupt or being wound up, and not barred from business.
  • No link to a consultant who prepared the design or specifications, and no conflict of interest with another tenderer (common control, subsidy, same legal representative, or influence over another tender).
  • Government-owned enterprises may tender only if legally and financially autonomous, operating under commercial law, and not dependent on the PE.
  • If awarded, you must disclose beneficial ownership in Form e-PG2-2 and consent to its publication after signing.

One tender only. Submitting or participating in more than one tender for the same item or lot gets all tenders with your participation rejected.

03Qualification Criteria

These are pass/fail. The TDS sets the exact figures; e-PG2 recommends these ranges, so you can estimate before reading the TDS.

CriterionTypical requirementEvidence
General experienceYears of supplying goods (at least 1 year is typical)Year of registration, constitution or licensing
Specific experienceAt least 1 similar contract completed in the last N years, worth 50% to 70% of the estimateCompletion certificate issued or certified by the PE
Financial resourcesLiquid assets, working capital or credit line of 80% to 100% of the estimateSee the liquid-asset options in section 05
LitigationPending litigation must not seriously affect your finances; all pending cases are treated as lostStatement on your letterhead
  • For several lots, your resources must meet the combined criteria of the lots you want to win.
  • You may not subcontract the supply or any part of it, before or after signing.

04Questions and Addenda

  • Ask for clarification through e-GP before the date in the IFT. The PE answers within 5 working days and need not answer late requests.
  • A pre-tender meeting, if any, is held online in e-GP. Answers appear on the dashboards of tenderers who bought the document. Missing it does not disqualify you.
  • Only a numbered, dated Addendum can change the document; meeting minutes cannot. Addenda come through e-GP and become part of the document.
  • If an addendum arrives with less than one-third of the preparation time left, the deadline is extended by at least 3 working days.

05Documents to Upload

DocumentWhat to check
Tender Submission Letter (e-PG2-1)Completed in e-GP without changing its format; you sign it by clicking "I agree" and Submit.
Tenderer Information (e-PG2-2)Legal status with names and NIDs of owners, partners or directors and 10%+ shareholders; litigation; experience; capacity; liquid assets; bank references.
Price Schedules (e-PG2-3A, 3B)Every item priced, with country of origin and manufacture.
Specifications Sheet (e-PG2-4)Country of origin, make and model, full specifications for every item and service.
Tender securityIf required, through an e-GP registered bank.
Trade licenseValid.
Tax documentsTIN certificate; income-tax return acknowledgement slip for the assessment year in the TDS; VAT registration / BIN.
Liquid-asset evidenceBank statement with the previous day's closing balance and 3 months of transactions; or updated balance on an approved credit line; or a credit commitment letter in Form e-PG2-7 from a scheduled bank. Issued no earlier than 28 days before the deadline.
Experience evidenceCompletion certificates for similar contracts.
Manufacturer's Authorisation (e-PG2-5)If the TDS requires it and you do not make the goods.
LTM enlistmentUpdated, valid enlistment letter from the PE.
OtherAny extra documents in the TDS; autonomy proof for government-owned enterprises; authority for the PE to seek bank references.

Tenders are written in English. Supporting documents in other languages need an accurate English or Bangla translation of the relevant parts, at your cost.

06Tender Security

  • Ask an e-GP registered bank to prepare the e-tender security for the TDS amount (a fixed sum, at most 3% of the official estimate) in favour of the PE.
  • Form: bank draft, pay order, or an irrevocable unconditional bank guarantee in Form e-PG2-6 from a scheduled bank, without alteration.
  • It must stay valid at least 28 days beyond tender validity. A tender without a valid security is non-responsive.
  • Return: non-responsive tenderers after the evaluation report is approved; the three lowest responsive tenderers after the contract is signed.

Your security can be forfeited if you:

  • Fail to furnish the performance security, or furnish one that is not authentic.
  • Refuse or fail to sign the contract.
  • Engage in corrupt, fraudulent, collusive, coercive or obstructive practice.

07Price Your Tender

  • Quote unit rates for every item in figures and words, excluding discounts, in Taka.
  • Each item must be priced for its full quantity, and a lot tender must cover 100% of its items and quantities. Leaving out an item worth more than 50% of the lot value makes the tender non-responsive.
  • Include all taxes, customs duties, VAT and levies as of 28 days before the deadline, plus profit, overheads, transport, insurance and banking charges up to the point of delivery.
  • Prices are fixed for the contract; they do not change with economic conditions. A later change in tax law is adjusted, subject to HOPE's approval.
  • Offer any unconditional discount, and how to apply it, in the Discount Form; for multi-lot discounts, state it per lot or combination.
  • e-GP does not correct arithmetic errors. If you find an error before submitting, correct it and have the authorised person initial it.

Two price traps: a tender more than 10% above the official cost estimate is rejected, and a tender below the Significantly Low-priced Tender limit (weighted average minus one standard deviation, using your rivals' prices, the estimate and the national price index) is rejected too. If yours is the only responsive tender, it must be within 20% of the estimate.

08Technical Compliance

  • Declare the country of origin of every item in the price schedules, with supporting evidence. Origin is where goods were produced or substantially transformed, not your nationality.
  • Prove conformity with literature, drawings and data: a detailed description of the essential technical and performance characteristics, and an item-by-item commentary on the PE's specifications.
  • Goods must be new, unused, of the latest models, and meet the stated standards (or, if none, the latest standards of the country of origin).
  • Minor deviations that do not meaningfully change specifications or commercial terms may be accepted; anything material will not.

09Submit Through e-GP

  1. Pay the document fee through an e-GP member bank by the day before the deadline, then download the e-TD.
  2. Check every file is virus-free, readable and complete. Corrupt or unreadable files are not considered.
  3. Allow time for large uploads; late submission is impossible in e-GP.
  4. Final-submit. Your e-signature authenticates the tender, it is stored encrypted, and you receive a confirmation e-mail.
  5. You can modify, substitute or withdraw only before the deadline. After it, no withdrawal is allowed.

The tender must remain valid for the days in the TDS after the deadline. The PE may ask, at most twice, to extend validity; you may refuse without losing your security, but your tender then drops out. If you agree, extend your security too and do not change your tender.

10How You Are Evaluated

  1. Preliminary: all forms signed, priced schedule, valid tender security and (LTM) enlistment letter. Anything missing means rejection.
  2. Technical: origin, conformity (Form e-PG2-4) and each qualification criterion, judged only on your tender.
  3. Financial: the 10% ceiling, any economic factors and discounts, then the SLT check.
  4. Post-qualification: your documents are verified, possibly with a visit to your premises. If you fail, the next lowest is considered.
  • The TEC may ask for clarifications (through e-GP, from the Chairperson) with at least 3 working days to reply. You cannot use a reply to change your tender. No reply may mean your tender is not considered.
  • From opening until the NOA, do not contact the PE except to answer a clarification or file a complaint. Trying to influence evaluation can make your tender non-responsive and lead to action under Section 64(5) of the PPA.
  • There are no negotiations. Ties are settled by checking for collusion, then past performance, then quality; never by lottery.

11Award and Contract Signing

  1. The NOA (Form e-PG2-8) arrives within 3 working days of approval. It states the price, performance security and deadlines, and with it you are bound by the contract.
  2. Quantities may be changed by up to the TDS percentage (max 20%) at award, at your quoted unit prices.
  3. Furnish the performance security of 10% of the contract price within 7 working days: bank draft, pay order or bank guarantee (Form e-PG2-10) from a scheduled bank, valid 28 days beyond completion. Government enterprises have 10% deducted from invoices instead.
  4. Sign the Contract Agreement (Form e-PG2-9) within 14 days. Failing to sign forfeits your tender security and the award goes to the next tenderer.
  5. Start supplying only after these steps. The PE publishes the contract and, for contracts above Tk. 10 lakh, your beneficial ownership details.

If you lose, you may ask for a debriefing on your own tender's weaknesses, and you may complain and appeal under Sections 29 and 30 of the PPA 2006 and Rules 72 to 77 of PPR 2025.

12Delivery, Payment and Warranty

Acceptance
Within 14 working days
Payment
100% on acceptance (90% if advance allowed)
Retention
10%, until warranty ends
Minimum warranty
3 months supplies, 1 year equipment
  • Pack goods to survive transit, with a packing list and the markings in the PCC; insure them until the PE accepts them; deliver to the site in the price schedule.
  • Carry out the tests in the PCC at your cost and report results. Rejected goods are rectified or replaced at your cost.
  • The TEAC starts inspection within 24 hours of delivery; the Acceptance Certificate follows within 14 working days (partial if defects are found).
  • Claim payment through e-GP with the invoice and delivery documents (invoice, delivery or truck receipt, warranty certificate, inspection certificate, certificate of origin as listed in the PCC). The PE pays within the PCC days and may owe interest if late.
  • Warranty starts when the delivery chalan is accepted. Repair or replace defective goods within the PCC days. Retention is released only if goods are free of patent and latent defects.
  • You bear all permits, licences, taxes and duties, and you indemnify the PE against intellectual-property claims.

13Delays, Penalties and Disputes

  • Need more time? Notify the PE in writing with the cause and duration before the original delivery date. The PE decides within 21 days; justified extensions carry no liquidated damages.
  • Liquidated damages: 0.03% to 0.05% per day (as in the PCC) of the value of late goods, up to a cap of no more than 10% of the contract price.
  • Force majeure: notify within 14 days; it excuses delay but not payment obligations.
  • Performance security claims: the PE may claim if a notified breach or unpaid amount continues for 14 days or more.

The PE may terminate for default, after a Notice of Default giving you 21 days to explain, if you:

  • Fail to deliver within the contract period or extension.
  • Fail to maintain a required security, or fail any other obligation.
  • Engage in corrupt, fraudulent, collusive, coercive or obstructive practice.
  • Reach the maximum liquidated damages, or assign any part of the supply to a subcontractor.

After termination you may be charged the PE's extra cost (15% to 25% of the revised estimate of the undelivered goods). Disputes go to amicable settlement, then the Adjudicator, then arbitration under the Arbitration Act 2001.

14Submission Checklist

  • You meet the experience, liquid-asset and litigation criteria in the TDS (and LTM enlistment, if LTM).
  • Forms e-PG2-1, 2, 3A/3B and 4 are complete and electronically signed.
  • Trade license, TIN, return acknowledgement for the TDS assessment year and VAT/BIN are uploaded.
  • Liquid-asset evidence is dated within 28 days of the deadline.
  • Tender security matches the TDS amount and is valid 28 days beyond tender validity.
  • Every item is priced for full quantity, all-inclusive, within 10% of the estimate and realistic against the SLT limit.
  • Specifications, origin, make and model and literature are provided for every item; Manufacturer's Authorisation if required.
  • Only one tender per item or lot, submitted well before the deadline.