e-PG3A · Goods Framework · For Procuring Entities

e-PG3A Framework Agreement Preparation Guideline

How to tender, evaluate and award a goods framework agreement under the Open or Limited Tendering Method, then buy against it through call-off orders, using BPPA's Standard Tender Document e-PG3A and the Public Procurement Rules 2025.

Based on e-PG3A, December 2025 (preliminary working draft) · Last reviewed 11 October 2026

Publishing Checklist All STD Guides

Bidding for a framework agreement instead? Read the e-PG3A participation guideline.

At a glance

  • One supplier, fixed unit rates, estimated quantities, normally 12 months.
  • Goods are bought through call-off orders; each order is delivered and paid on its own.
  • Works with OTM or LTM; LTM tenderers must be enlisted with you.
  • Award to the lowest evaluated responsive tender after the SLT check.
  • You guarantee a minimum order value stated in the Schedule of Requirements.

For Procuring Entity officials, Tender Evaluation Committee members, inspection committees and officers who issue call-off orders.

This is a working summary of a draft document. BPPA issued e-PG3A in December 2025 as a preliminary working draft and asks PEs to contact BPPA if anything is unclear. The STD in e-GP, the Public Procurement Act 2006 and the Public Procurement Rules 2025 take priority over this guide.

On this page

Before you start

01When to Use e-PG3A 02How a Framework Agreement Works 03How the Document Works 04Key Time Limits

Prepare and publish

05Fill In the TDS 06Fill In the PCA 07Quantities and Price Schedule 08Clarifications and Addenda

Evaluate and award

09Opening and Preliminary Check 10Technical Evaluation 11Financial Evaluation and SLT 12Post-qualification and Award

Run the agreement

13Issuing Call-off Orders 14Contract Management 15Publishing Checklist 16Common Questions

01When to Use e-PG3A

Use e-PG3A when the Procuring Entity (the Purchaser) wants an agreement for a definite period with a single supplier for a fixed or estimated quantity of goods and related services, where the actual deliveries happen through several call-off orders. Specifications and quantities are defined up front and the overall delivery period is fixed, so a total agreement amount can be calculated.

Nature
Goods and related services
Method
Open (OTM) or Limited (LTM) Tendering
Arrangement
Framework Agreement with one supplier
Period
Set in the PCA, normally 12 months
Award basis
Lowest evaluated responsive
Buying
Call-off orders, each paid separately
  • Good fits: recurring needs such as consumables, stationery, spare parts, medicines or fuel, where you know the specification and roughly how much you will use, but not exactly when.
  • "Goods" includes commodities, raw material, machinery, equipment and industrial plants, and where applicable related services such as transport, insurance, installation, commissioning, training and initial maintenance.
  • The supplier cannot deliver without a call-off order (requisition slip) issued by your office under the agreement.

02How a Framework Agreement Works

  1. Tender once. Publish e-PG3A in e-GP with estimated quantities, specifications, delivery points and the agreement period.
  2. Award the agreement. Evaluate, post-qualify, issue the NOA, take the performance security and sign the Framework Agreement (Form e-PG3A-10). Unit rates are now fixed.
  3. Order as needed. During the period, issue a call-off order for the quantity, place and timing you need. Each call-off is a contract between the Purchaser and the Supplier.
  4. Receive and accept. The supplier delivers within the response time; the inspection committee checks the goods and an Acceptance Certificate follows.
  5. Pay the call-off. The supplier invoices through e-GP; you pay the call-off value (quantity × contract unit rate). Repeat from step 3 until the period ends.
The main differences from a one-off goods tender under e-PG3.
Topice-PG3 (one-off contract)e-PG3A (framework)
MethodOTMOTM or LTM
QuantitiesFirmEstimated; minimum order value guaranteed
DeliveryFixed scheduleAs per each call-off order
PaymentAgainst the contractAgainst each call-off order
ConditionsGCC / PCCGCA / PCA (General and Particular Conditions of Agreement)
Price above estimateOver 10% rejectedNo automatic exclusion above or below the estimate
Liquidated damages0.10% to 0.15% per day0.05% to 0.10% per day
PE's own extension powerUp to 30% of original timeUp to 20% of original time

03How the Document Works

e-PG3A has six sections. Sections 1 (ITT) and 3 (GCA) must not be altered. You adapt the document to your package only through the TDS, the PCA, the Price Schedule, the Technical Specifications and any Drawings.

PartWhat it contains
Section 1. ITTInstructions to Tenderers: preparation, submission, opening, evaluation, qualification and award. Not edited and not part of the contract.
Section 2. TDSPackage-specific values, numbered to match the ITT clauses.
Section 3. GCAGeneral Conditions of Agreement for the framework. Not edited.
Section 4. PCAParticular Conditions of Agreement that modify or supplement the GCA, numbered to match.
Tender formse-PG3A-1 Submission Letter; e-PG3A-2 Tenderer Information; e-PG3A-3 Subcontractor Information; e-PG3A-4A/4B Price Schedules; e-PG3A-5 Specifications Sheet; e-PG3A-6 Manufacturer's Authorisation; e-PG3A-7 Tender Security guarantee; e-PG3A-8 Credit Line commitment.
Contract formse-PG3A-9 Notification of Award; e-PG3A-10 Framework Agreement; e-PG3A-11 Performance Security guarantee; e-PG3A-12 Advance Payment guarantee; e-PG3A-13 Agreement Amendment; Call-Off Order form.
Section 6. DrawingsDated, numbered drawings that supplement the specifications, if any.
Annex formatsA: Invitation for Tenders; B: Reporting Agreement Award; C: Public Reporting on Agreement Signing; D: Acceptance Certificate. For information only.

04Key Time Limits

StepTime limitReference
Answer a clarification requestWithin 5 working days, through e-GPITT 9.3
Send pre-tender meeting minutesWithin 5 working days of the meetingITT 10.3
Circulate an addendumWithin 5 working days of issueITT 11.2
Extend deadline for a late addendumAt least 3 working days, if under one-third of the preparation time remainsITT 11.5
Tenderer's reply to a TEC clarificationNot less than 3 working daysITT 45.4
Notice of rejection of all tendersWithin 3 working days of HOPE's decisionITT 57.1
Issue the NOAWithin 3 working days of award approval, before validity expiresITT 60.1
Publish the awardWithin 24 hours of the NOA; display for 28 daysITT 61.1
Performance security7, 10 or 14 working days of the NOA (see below)TDS 62.1, Rule 123(7)
Sign the agreement14, 21 or 28 days of the NOA (see below)TDS 67.2, Rule 123(9)
Publish agreement signingWithin 3 days of signing; display for 30 daysITT 68.1
Advance payment, if anyWithin 30 days of signingPCA 26.1(a)
Supplier declines a small call-off, or resets the response time on a large oneSupplier's notice within 3 working days of the orderForm e-PG3A-10, item 10
Start acceptance inspectionWithin 24 hours of deliveryGCA 23.2
Issue Acceptance CertificateWithin 14 working days of receipt at destinationGCA 23.1
Decide a delivery extension requestWithin 21 days of the supplier's noticeGCA 33.3
Return performance securityWithin 28 days of completion and the Acceptance Certificate, after warrantyGCA 29.4, 29.5
Performance security and signing deadlines depend on the estimated cost (Rule 123 of PPR 2025).
Estimated costPerformance securitySign agreement
Up to Tk. 5 crore7 working days14 days
Above Tk. 5 crore, up to Tk. 25 crore10 working days21 days
Above Tk. 25 crore14 working days28 days

ITT 63.2 also says "within fourteen (14) days" for the performance security. Use the TDS figure from the table above, which follows Rule 123(7), and state it in the NOA.

05Fill In the TDS

These are the TDS entries e-PG3A asks for, with the values or ranges the document recommends.

TDSWhat to stateGuidance in e-PG3A
ITT 1.1PE name, tender name, tender reference, lot numbersIdentify lots consistently with the Price Schedule.
ITT 3.1, 3.3Source of funds; development partner, if anyGoB or other source.
ITT 3.4Who pays each call-off orderThe PE and/or another unit of the same department or division.
ITT 5.1, 6.1Ineligible countries for tenderers and goodsOnly if applicable.
ITT 13.1(a)Years of general supply experienceAt least 3 years is reasonable; count back from the IFT date.
ITT 13.1(b)Number of similar contracts completed in the last N years, each of at least Tk. XFor large supply, one contract in 5 or 10 years may suit; value 60% to 80% of the estimated cost; state per lot.
ITT 13.1(c)Minimum supply or production capacity per year, by type and quantityUsually twice the required quantity; up to five times for common goods; state per lot.
ITT 14.1(b)Minimum liquid assets, working capital or credit line80% to 100% of the estimated cost; state per lot.
ITT 20.1(h)Income-tax assessment yearThe immediate past assessment year of the financial year the tender is invited in.
ITT 20.1(k)Any additional documentsList them, if any.
ITT 21.1(b)LTM only: whether tender security is requiredState it if you want security from enlisted tenderers.
ITT 28.1(d)Litigation history periodConsistent with the general-experience years.
ITT 28.1(f)Manufacturer's Authorisation: none, all items, or listed itemsUsually not needed for off-the-shelf goods.
ITT 28.1(h)Years of audited financial statementsOnly for tenderers showing working capital; consistent with experience years.
ITT 29.1Tender validity in daysNormally 60 to 150 days.
ITT 31.1Tender security amount and beneficiaryA fixed amount not exceeding 3% of the official estimate; may differ per lot.
ITT 48.6Economic factors, if usedLate-delivery adjustment (% per day, with a limit beyond which tenders are rejected) and/or cost of spare parts for an initial period; delete if not used.
ITT 59.1Quantity variation at awardUp to 20% increase or decrease.
ITT 62.1Performance security amount and time10% of the contract price; 7, 10 or 14 working days by estimated cost.
ITT 62.3Security deposit for a government-owned enterprise10% deducted from payable invoices.
ITT 66.1, 66.3Retention money; contractual security cap10% retention from the payment certificate; contractual security not beyond 10% of the contract price.
ITT 67.2Agreement signing time14, 21 or 28 days by estimated cost.
ITT 70.1Proposed Adjudicator, hourly fee, reimbursables, biodataName and address of the proposed person.

As written, the TDS sets a 10% performance security and 10% retention, but caps the combined contractual security at 10% of the contract price. Confirm with BPPA how to apply the cap before you publish, and keep the TDS internally consistent.

The pre-tender meeting, if any, is held online in e-GP on the date and time in the Invitation for Tenders, and the IFT also sets the last date for clarification requests.

06Fill In the PCA

PCAWhat to stateGuidance in e-PG3A
GCA 1.1(q), (v)PE name; sites or points of deliveryFull name; detailed location of every delivery point.
GCA 3.1Notice addresses for both partiesAttention, address, phone, fax, e-mail.
GCA 4.1Framework Agreement period and startNormally 12 months; a specific date or the date of acceptance.
GCA 8.1(i)Other documents forming the agreementName them.
GCA 9.1Scope of supplyAs in the Price Schedule, adjusted for any quantity variation at award.
GCA 11.1, 11.2Ineligible supplier or subcontractor nationalities; goods originsOnly if applicable.
GCA 21.2Packing, marking and documentationMark outer packing on at least four sides: PE, supplier, agreement, destination, weight, package number, contents, lifting and handling.
GCA 22.3Delivery documentsInvoice with description, quantity, unit price and total; delivery note or truck/railway receipt; warranty certificate; inspection certificate; certificate of origin, as needed.
GCA 24.1Original contract priceThe amount in the NOA.
GCA 26.1(a)Advance payment, if admissibleRecommended maximum 10% of the original price, paid within 30 days of signing against an original bank guarantee (Form e-PG3A-12) valid until delivery. Delete if not used.
GCA 26.1(b)Payment on delivery and acceptance90% of each call-off order price if an advance is paid, otherwise 100%; call-off price = quantity × contract unit rate.
GCA 26.3, 26.5Days to pay after an accepted invoice; late-payment interestYour own assessment; prevailing commercial rate or "None".
GCA 31.1Inspections and testsGoods, type of test, time or milestone, place and procedure, where special tests are needed.
GCA 32.3, 32.7Warranty period; days to correct defectsGCA minimum is 3 months for supplies and 1 year for equipment.
GCA 34.1Liquidated damages rate and cap0.05% to 0.10% per day of the value of undelivered goods; cap not more than 10% of the final contract price.
GCA 43.2(b), (e)Adjudicator; appointing authorityName and contacts; appointing authority is the President of IEB.
GCA 43.3(b)Arbitration venuePlace, location and district.

07Quantities and Price Schedule

Form e-PG3A-4A covers goods (including spare parts) and Form e-PG3A-4B covers related services. For each item, set the description, unit, estimated quantity and the point(s) of delivery; tenderers enter country of origin and manufacture and the unit price, and the delivery period reads "as per call-off order".

  • Quantities are estimates. Base them on past consumption and the agreement period: too high misleads tenderers on scale, too low leaves you short.
  • Set the minimum order value and the response times for call-offs in the Schedule of Requirements. You guarantee to order at least that value, and the supplier is held to those response times.
  • List every delivery point. One item may be delivered to several places.
  • For e-GP, tenders are invited for a single lot, and alternative tenders are not allowed.
  • Write specifications and standards in the Technical Specifications and Drawings. Tenderers answer them in Form e-PG3A-5 with origin, make and model and full specifications.
  • Document sale has no preconditions and stays open until the day before the deadline.

08Clarifications and Addenda

  1. Set in the IFT the last date for clarification requests. Requests come through e-GP; answer within 5 working days and share the answer with all buyers of the document without naming the source. You need not answer late requests.
  2. A pre-tender meeting, if held, is online in e-GP. Answers go to the dashboards of tenderers who bought the document; send minutes within 5 working days, also to those who did not attend. Missing the meeting does not disqualify anyone.
  3. Change the document only by an Addendum issued in e-GP before the deadline, dated and numbered, and circulated within 5 working days. Never change it through meeting minutes.
  4. Post the addendum, with its number and date, on your website and the notice boards where the IFT was posted.
  5. If an addendum is issued when less than one-third of the preparation time remains, extend the deadline by at least 3 working days.

09Opening and Preliminary Check

e-GP opens tenders automatically after the deadline and generates the Tender Opening Report. Late tenders cannot be submitted. The TEC then evaluates in four steps: preliminary examination, technical responsiveness, financial evaluation and post-qualification, completing the Tender Evaluation Reports that e-GP generates.

A tender is rejected at the preliminary stage if any of these is missing:

  • All applicable forms, filled in and electronically signed.
  • The priced schedule.
  • A valid tender security.
  • Under LTM, the letter of enlistment with your PE.

10Technical Evaluation

  • Judge responsiveness on the contents of the tender only, without outside evidence. There is no minimum number of responsive tenders.
  • A material deviation, reservation or omission (one that substantially affects scope, quality or supply; limits the PE's rights or the tenderer's obligations; or would unfairly affect competitors if corrected) makes a tender non-responsive, and it cannot be cured afterwards.
  • Check, in order: the country-of-origin declaration in Forms 4A/4B, conformity in Form e-PG3A-5 and its evidence, then each qualification criterion (experience, capacity, liquid assets, litigation).
  • Subcontracting is limited to 30% of the goods value and must be declared in Form e-PG3A-3. Each subcontractor must meet the eligibility rules; you may ask for more information or a substitute.
  • You may ask a responsive tenderer to fix non-material documentary omissions, but never anything touching rates or mandatory criteria.
  • Clarification requests go through e-GP from the TEC Chairperson only, allow at least 3 working days, and must not change the substance of the tender.

11Financial Evaluation and SLT

  • e-GP has no arithmetic-correction step.
  • There is no automatic exclusion of tenders above or below the official estimate. A price above a realistic estimate is a ground for rejecting all tenders, not for rejecting one.
  • Evaluate the tender price adjusted for any equivalent-lot-value method, TDS economic factors and unconditional discounts. Ignore unsolicited extras.
  • If a tenderer offered only 80% of a lot's items (where permitted), add the average prices of other responsive tenderers for the missing items. If the winning lot misses 20% or fewer items, buy them from the tenderer offering them at least cost.
  • If item prices look unbalanced, the TEC may recommend raising the performance security up to 25% of the contract price.

With at least two technically responsive tenders, screen for a Significantly Low-priced Tender (ITT 50):

x̄ = 0.5 × (average of quoted prices) + 0.2 × official cost estimate + 0.3 × XNPPI

Sd = √( Σ (x̄ − xi)² / n )    Lower limit = x̄ − Sd

  • XNPPI is the official cost estimate multiplied by the National Public Procurement Price Index: the national average deviation between estimate and awarded price for goods, from e-GP awards over the 28 days ending on the opening day (excluding national LTM).
  • Any tender below the lower limit is financially non-responsive and rejected.
  • With only one responsive tender, compare its price with the official estimate instead: more than 20% deviation makes it non-responsive.
  • The lowest-priced technically and financially responsive tender is the lowest evaluated responsive tender.

On a tie, first look for collusion (Rule 149 of PPR 2025). Without it, prefer the tenderer with better past performance with the PE, then the quality more advantageous to end-users. Never use a lottery, and hold no negotiations.

12Post-qualification and Award

  1. Post-qualify the lowest evaluated tenderer on its submitted eligibility and qualification evidence only; the TEC may visit its premises. If it fails, move to the next lowest.
  2. After approval, issue the NOA (Form e-PG3A-9) within 3 working days and before validity expires, stating the price, performance security amount and form, and the deadlines for security and signing. Quantities may vary up to the TDS percentage (max 20%) without changing unit prices.
  3. Within 24 hours of the NOA, publish the award (Format e-PG3A-B) on your notice board or website and on the BPPA website, for at least 28 days.
  4. Send the draft Framework Agreement (Form e-PG3A-10) with the NOA. Receive the 10% performance security and sign within the TDS deadlines. If the tenderer fails to furnish security or sign, annul the award, forfeit its tender security and go to the next lowest qualified tenderer.
  5. Within 3 days of signing, publish the agreement information with beneficial ownership details (Format e-PG3A-C) for at least 30 days; beneficial ownership is required above Tk. 10 lakh.
  6. Return tender securities: non-responsive ones after the evaluation report is approved; the 1st to 3rd lowest once the winner furnishes performance security and signs.

All tenders may be rejected only on HOPE's approval and for the reasons in ITT 56.2 (price above a realistic estimate, lack of competition, unrealistic completion, all non-responsive, defects in the process, or misconduct), but not if the lowest price matches the market price.

13Issuing Call-off Orders

Every purchase under the agreement is a call-off order on the form attached to the agreement, signed by the official authorised to issue call-offs. Each order states:

  • The contract (agreement) reference, a call-off order reference and its date.
  • The purchaser and the supplier.
  • The list of supplies with quantities, unit rates from the Price Schedule and delivery places.
  • The total value of the call-off, and a request that the supplier confirm receipt and proceed within the agreed response times.
RuleWhat it means for you
PeriodOrders may be issued during one year from the agreement date (or the PCA period). An order issued in the period but not yet completed is still governed by the agreement.
Exclusive useOrder all your requirements for these supplies from the supplier during the period, unless an emergency need cannot be met within the time you require.
Minimum valueYou guarantee to order at least the minimum value in the Schedule of Requirements. Ordering less than the estimated quantities gives no right to an adjustment.
Small ordersIf an order is under 2½% of the agreement price, the supplier may decline it by notice within 3 working days.
Large ordersIf one order, or all orders in a month, exceed 25% of the agreement price, the supplier may give notice within 3 working days and set a longer delivery period instead of the response time.
ConflictsIf a call-off order conflicts with the agreement, the agreement prevails.

Example: agreement price Tk. 2 crore An order below Tk. 5 lakh (2½%) can be declined by the supplier. If one order, or a month's orders together, exceed Tk. 50 lakh (25%), the supplier may set its own delivery period. Plan regular orders between these two limits to keep the agreed response times.

14Contract Management

  • Delivery: the supplier delivers to the places and within the times in each call-off and gets a receipt. Title passes on satisfactory delivery, but delivery is not acceptance; you may reject goods that do not meet the specification.
  • Acceptance: the inspection committee starts within 24 hours of delivery; issue the Acceptance Certificate (Format e-PG3A-D) within 14 working days, for accepted parts only if defects are found.
  • Payment: any advance within 30 days of signing; each call-off is paid on the supplier's e-GP invoice with the delivery documents, in Taka, within the PCA days. Pay interest on late payment if the PCA provides it.
  • Securities: notify the supplier of any claim on the performance security; claim only if a notified breach or unpaid amount continues for 14 days or more. Release it after the warranty period if goods are free of patent and latent defects.
  • Warranty: starts when the delivery chalan is accepted, so each delivery's warranty ends at a different time. Track it per call-off.
  • Change orders: drawings or specifications for custom goods, packing, delivery place or related services, with an equitable price or time adjustment. Repeat orders within the warranty only in exceptional cases, after price verification and the Approving Authority's approval.
  • Extensions: the supplier must apply before the original date; decide within 21 days. The PE may extend up to 20% of the original time; beyond 20% needs HOPE's or the authorised officer's approval and an amendment (Form e-PG3A-13).
  • Liquidated damages: T = V × P × n, where V is the value of undelivered goods, P the PCA rate per day and n the days of delay, up to the PCA cap.
  • Termination: for default with 28 days' written notice (late delivery, other breach, corrupt practice, or LD at maximum), buying the remainder elsewhere at the supplier's extra cost; for insolvency; or for convenience with 28 days' notice.
  • Disputes: amicable settlement, then the Adjudicator (referral within 14 days, decision within 28 days; the supplier pays the fees and the PE reimburses half), then arbitration under the Arbitration Act 2001.

15Publishing Checklist

  • A framework suits the need: defined specification, recurring demand, estimated quantities, and OTM or LTM is the right method.
  • Agreement period, delivery points, minimum order value and call-off response times are stated.
  • Experience (60% to 80%), capacity (2 to 5 times the quantity) and liquid-asset (80% to 100%) thresholds are set against the estimate, per lot.
  • Assessment year, financial-statement years, validity (60 to 150 days) and tender security (up to 3%, fixed) are filled in; LTM security choice made.
  • Performance security and signing deadlines match the estimated-cost band; the contractual security cap is consistent.
  • Manufacturer's Authorisation, economic factors and advance payment are either specified or deleted.
  • Price Schedules 4A/4B list every item with unit, estimated quantity and delivery point.
  • PCA payment per call-off, warranty, LD rate (0.05% to 0.10% per day) and cap, and dispute details are filled in.
  • The officer authorised to sign call-off orders is named.
Setting up your first framework agreement?

Bidorix can review your TDS, PCA, quantities and call-off arrangements before you publish.

Request Assistance Ask a Question

16Common Questions

Do we have to buy the full estimated quantity?

No. Quantities in the Schedule of Requirements are estimates, and ordering less is not a ground for an adjustment. You must, however, order at least the minimum value stated there, and buy these supplies from the framework supplier during the period except in an emergency it cannot meet.

Can several offices order under one agreement?

The TDS (ITT 3.4) names who pays for each call-off: the PE and/or another unit of the same department or division. Name every paying unit and every delivery point before you publish.

Is a tender priced more than 10% above our estimate rejected?

Not under e-PG3A. ITT 44.5 says there is no automatic exclusion of tenders above or below the estimate. You may still reject all tenders, with HOPE's approval, if the lowest price exceeds a realistic estimate and does not reflect the market price.

Can we change unit rates during the agreement?

No. Prices are fixed and do not move with economic conditions. They change only through a change order, a repeat or additional order, or a change in Bangladesh law that affects price or delivery.

What if the supplier refuses an order?

It may decline only an order below 2½% of the agreement price, by notice within 3 working days. Any other refusal or late delivery is a breach: liquidated damages apply, and you may terminate for default with 28 days' written notice.