e-PG4 International Goods Preparation Guideline
How to prepare, publish, evaluate, award and administer an international goods tender of any value under the Open Tendering Method, using BPPA's Standard e-Tender Document e-PG4 and the Public Procurement Rules 2025.
Submitting a tender instead? Read the e-PG4 participation guideline.
This is a working summary, not the official document. The e-PG4 STD issued by BPPA, the Public Procurement Act 2006 and PPR 2025 take priority, together with any development partner agreement that finances the package. Use the version attached in e-GP for your package.
01When to Use e-PG4
Use e-PG4 when the Procuring Entity (the Purchaser) wants to buy goods and related services through international competition under the Open Tendering Method in e-GP, for any value. The contract goes to the lowest evaluated responsive tender.
- Nature
- Goods and related services
- Method
- Open Tendering (OTM)
- Competition
- International
- Value
- Any value
- Award basis
- Lowest evaluated responsive
- Channel
- e-GP system
| Topic | e-PG3 (national) | e-PG4 (international) |
|---|---|---|
| Value | Above Tk. 50 lakh | Any value |
| Price schedules | Goods and services | 4A made in Bangladesh, 4B to be imported, 4C already imported, 4D services |
| Currency | Taka only | Taka plus one foreign currency (USD, GBP, EUR or JPY) |
| Domestic preference | None | 15% for qualifying Bangladesh-made goods |
| Low-price check | SLT formula | No SLT clause |
| Performance security bank | Scheduled bank of Bangladesh | Internationally reputable bank with a correspondent bank in Bangladesh |
| Liquidated damages | 0.10% to 0.15% per day | 0.03% to 0.05% per day |
| Arbitration | Arbitration Act 2001 | International rules for foreign suppliers; Arbitration Act 2001 for national suppliers |
Need the equipment installed, tested and commissioned as a working facility by one contractor? That is a turnkey tender under e-PG5A (International).
02How the Document Works
You adapt e-PG4 only through the TDS, the PCC, the Schedule of Requirements, the Technical Specifications and any Drawings. Specify in the TDS only what the ITT says should go there.
| Part | What it contains |
|---|---|
| Section 1. ITT | e-submission, opening, evaluation, domestic preference, qualification and award. |
| Section 2. TDS | Package-specific values, numbered to match the ITT. |
| Section 3. GCC | General Conditions of Contract, including a formal termination procedure. |
| Section 4. PCC | Clauses that modify or supplement the GCC: shipping documents, payment, insurance, arbitration rules. |
| Tender forms | e-PG4-1 Submission Letter; e-PG4-2 Tenderer Information; e-PG4-3 Subcontractor Information; e-PG4-4A/4B/4C goods and 4D services Price Schedules; e-PG4-5 Specifications Sheet; e-PG4-6 Manufacturer's Authorisation; e-PG4-7 Tender Security guarantee; e-PG4-8 Credit Line commitment. |
| Contract forms | e-PG4-9 Notification of Award; e-PG4-10 Contract Agreement; e-PG4-11 Performance Security guarantee; e-PG4-12 Advance Payment guarantee; e-PG4-13 Contract Amendment. |
| Schedule of Requirements | List of goods with delivery points and earliest and latest delivery dates; list of related services with completion dates. |
| Technical Specifications | Prepared under Rule 38 of PPR 2025, with the tests and inspections you require. |
| Section 6. Drawings | Dated, numbered drawings, if any. |
03Key Time Limits
| Step | Time limit | Reference |
|---|---|---|
| Answer a clarification request | Within 5 working days, through e-GP | ITT 9.3 |
| Send pre-tender meeting minutes | Within 5 working days of the meeting | ITT 10.3 |
| Circulate an addendum | Within 5 working days of issue | ITT 11.2 |
| Extend deadline for a late addendum | At least 3 working days, if under one-third of the preparation time remains | ITT 11.5 |
| Tenderer's reply to a TEC clarification | Not less than 3 working days | ITT 44.4 |
| Notice of rejection of all tenders | Within 3 working days of HOPE's decision | ITT 58.1 |
| Issue the NOA | Within 3 working days of award approval, before validity expires | ITT 61.1 |
| Publish the award | Within 24 hours of the NOA; display for 28 days | ITT 62.1 |
| Performance security | 7, 10 or 14 working days of the NOA (see below) | TDS 63.1, Rule 123(5) |
| Sign the contract | 14, 21 or 28 days of the NOA (see below) | TDS 68.2, Rule 123(9) |
| Publish contract signing | Within 3 days of signing; display for 30 days | ITT 69.1 |
| Advance payment, if any | Within 30 days of signing | PCC 25.1 |
| Shipping documents reach the PE | At least one week before the goods arrive | GCC 21.2 |
| Start acceptance inspection | TEAC within 24 hours of delivery | GCC 22.2 |
| Issue Acceptance Certificate | Within 14 working days of receipt at final destination | GCC 22.1 |
| Decide a delivery extension request | Within 21 days of the supplier's notice | GCC 33.3 |
| Return performance security | Within 7 days of final payment and the Acceptance Certificate | GCC 28.4 |
| Estimated cost | Performance security | Sign contract |
|---|---|---|
| Up to Tk. 5 crore | 7 working days | 14 days |
| Above Tk. 5 crore, up to Tk. 25 crore | 10 working days | 21 days |
| Above Tk. 25 crore | 14 working days | 28 days |
ITT 64.2 still says the performance security is due within 28 days of the NOA, while the TDS sets 7, 10 or 14 working days under Rule 123(5). Use the TDS figure and state it in the NOA, so the supplier is not misled.
04Fill In the TDS
| TDS | What to state | Guidance in e-PG4 |
|---|---|---|
| ITT 1.1 | PE name, tender name, reference, lot numbers | Identify lots consistently with the Schedule of Requirements. |
| ITT 3.1, 3.3 | Source of funds; development partner, if any | GoB or other source. |
| ITT 5.1, 6.1 | Ineligible countries for tenderers, goods and services | Only if applicable. |
| ITT 13.1(a) | Years of general supply experience | 3 or 5 years would be reasonable; count back from the IFT date. |
| ITT 13.1(b) | Similar contracts completed in the last N years, each of at least Tk. X | Value 60% to 80% of the estimated cost; state per lot. |
| ITT 13.1(c) | Supply or production capacity per year | Usually twice the requirement; up to five times for common goods; per lot. |
| ITT 14.1(b) | Minimum liquid assets, working capital or credit line | 80% to 100% of the estimated cost; per lot. |
| ITT 15.1 | Percentage of goods that may be subcontracted | Maximum 30% of the goods value. |
| ITT 20.1(h) | Income-tax assessment year | The immediate past assessment year of the financial year the tender is invited in. |
| ITT 20.1(o) | Additional documents | List them, if any. |
| ITT 23.15(c), 23.16(c), 23.17(e) | Final destination (project site) | Where the goods will be used or delivered. |
| ITT 23.16(a), (d) | Named place or port for CIP/CIF; any other INCOTERM | If another INCOTERM is used, customise Form 4B. |
| ITT 24.3 | Foreign currency allowed | One of USD, GBP, EUR or JPY. |
| ITT 26.3(b) | Spare parts list required or not, and the operating period | Supplier-recommended spares are not counted in evaluation. |
| ITT 27.1(e) | Litigation history period | Consistent with the general-experience years. |
| ITT 27.1(g) | Manufacturer's Authorisation: none, all items, or listed items | Usually not needed for off-the-shelf goods. |
| ITT 27.1(h) | After-sales service required or not | For a foreign tenderer, a local agent able to carry out maintenance. |
| ITT 27.1(j) | Years of audited financial statements | Only for tenderers showing working capital. |
| ITT 28.1 | Tender validity | Normally 60 to 150 days (Rules 28 and 29). |
| ITT 30.1 | Tender security in Taka or US dollar equivalent, and beneficiary | A rounded fixed amount, not more than 3% of the estimate, never a precise percentage (Rule 31). |
| ITT 48.1 | Domestic preference "shall" or "shall not" apply | Applies unless you say otherwise. |
| ITT 49.6 | Economic factors | Late-delivery adjustment and/or spare-parts cost; delete if not used. |
| ITT 60.1 | Quantity variation at award | Up to 20% increase or decrease. |
| ITT 63.1, 63.2 | Performance security amount and time | 10% of the contract price; 7, 10 or 14 working days. |
| ITT 63.4 | Security deposit for a government-owned enterprise | 10% deducted from invoices. |
| ITT 67.1, 67.3 | Retention; contractual security cap | 10% retention; cap 10% of the contract price. |
| ITT 68.2 | Contract signing time | 14, 21 or 28 days by estimated cost. |
| ITT 71.1 | Proposed Adjudicator, hourly fee, reimbursables, biodata | Name and address. |
As in other PPR 2025 goods STDs, the TDS sets a 10% performance security and 10% retention but caps their total at 10% of the contract price. Confirm with BPPA how to apply the cap before you publish.
05Price Schedules, INCOTERMs and Currency
Tenderers choose the schedule that fits the origin of each item. Splitting the price this way lets you compare tenders fairly and apply domestic preference; it does not limit your right to contract on any of the terms offered.
| Form | Used for | Price columns |
|---|---|---|
| e-PG4-4A | Goods made in Bangladesh (Group A) | EXW price including duties already paid on components; Supplier's VAT; inland transport and insurance to the final destination; local labour, materials and components as a % of EXW. |
| e-PG4-4B | Goods made abroad, to be imported (Group B) | CIP (named place) or CIF (named port) in foreign currency; Supplier's VAT; inland transport and insurance to the final destination. |
| e-PG4-4C | Goods made abroad, already imported (Group B) | Price including duties paid; duties, import VAT and taxes paid, with evidence; price net of those; Supplier's VAT; inland transport. |
| e-PG4-4D | Related services | Unit price inclusive of applicable taxes; excludes inland transport needed to deliver the goods. |
- Currencies: local expenditure in Taka; expenditure outside Bangladesh in the one foreign currency named in the TDS (USD, GBP, EUR or JPY). Bangladesh manufacturers may combine local and foreign currency.
- Conversion: for evaluation, the TEC converts everything to Taka at Bangladesh Bank's selling rate on the opening date.
- Taxes in evaluation: the Supplier's VAT on local goods, and customs duties and import taxes on imported goods, are left out of the comparison but are part of the contract price.
- Carriers and insurers: tenderers may use transport and insurance from any eligible country.
- For e-GP, tenders are invited for a single lot, and alternatives are not allowed. Prices are fixed.
06Fill In the PCC
| PCC | What to state | Guidance in e-PG4 |
|---|---|---|
| GCC 1.1(o), (t) | PE name; sites or points of delivery | Full name and location details. |
| GCC 3.1 | Notice addresses for both parties | Attention, address, phone/cell, fax, e-mail. |
| GCC 7.1(i), 8.1 | Other contract documents; scope of supply | Scope as in the Schedule of Requirements, adjusted for any quantity change at award. |
| GCC 10.1, 10.2 | Ineligible nationalities and origins | Only if applicable. |
| GCC 16.1, 17.3 | Responsibilities of the supplier and of the PE | Specify them. |
| GCC 20.2 | Packing, marking and documentation | Outer packing marked on at least four sides. |
| GCC 21.1, 21.2 | Shipping notice and documents | For CIF/CIP/DDP from abroad: notify the PE and insurer of shipment details; invoice, bill of lading, packing list, insurance certificate, warranty, inspection certificate, certificate of origin. For EXW/DDP from within Bangladesh: invoice, delivery note, warranty, inspection certificate, origin certificate. |
| GCC 23.1, 24.2 | Contract price; transport responsibilities | As per the INCOTERM in the price schedule. |
| GCC 25.1 | Payment method | See the payment example below. |
| GCC 25.3, 25.5 | Days to pay; late-payment period and interest rate | 30, 45 or 60 days, for example; interest normally 1% above the scheduled banks' lending rate. |
| GCC 26.2 | Insurance coverage | Coverage, currency and amount. |
| GCC 29.1 | Retention | 10% of the contract price. |
| GCC 31.1 | Inspections and tests | Type, time or milestone, place, procedure. |
| GCC 32.3, 32.7 | Warranty period and final destination; days to correct defects | GCC minimum is 3 months for supplies and 1 year for equipment. |
| GCC 34.1 | Liquidated damages rate and cap | 0.03% to 0.05% per day of the contract value; cap not more than 10% of the final contract price. |
| GCC 41.8 | Extra cost on termination for default | 15% to 25% of the revised estimate of the incomplete supply. |
| GCC 46.2(b), (e) | Adjudicator and appointing authority | Name both. |
| GCC 46.3(b) | Arbitration rules | Foreign supplier: international rules such as UNCITRAL, ICC, LCIA or Stockholm Chamber (do not name the World Bank as arbitrator). National supplier: Arbitration Act 2001. |
- Imported goods: advance
- Up to 10%, within 30 days of signing
- Imported goods: on shipment
- 80% by irrevocable confirmed L/C
- Imported goods: on acceptance
- 10% within 30 days of receipt
- Local goods: on acceptance
- 90% with advance, 100% without
This is the PCC's sample payment provision; adapt it to your package. For 100% GoB-funded procurement, advance payment does not apply unless the Government specifically decides otherwise. Advances need an original bank guarantee in Form e-PG4-12.
07Schedule of Requirements and Specifications
- List of Goods: item, unit, quantity, final destination and the earliest and latest delivery dates in weeks, counted from contract signing (or L/C opening or confirmation, as you choose). You may include a limited supply of fast-moving or hard-to-find spare parts.
- List of Related Services: assembly or start-up, tools, operation and maintenance manuals, maintenance or repair for a period, and training, with the place and completion date. Use "1" or "lump sum" where units do not apply.
- Technical Specifications: follow Rule 38 of PPR 2025. Allow the widest possible competition, state the standards, require new and current-model goods, and say which tests you require and where.
- Site visits: for goods needing installation, commissioning or networking, tenderers are encouraged to visit the site at their own cost and must tell you in advance.
08Clarifications and Addenda
- Set the last date for clarification requests in the IFT. Requests come through e-GP; answer within 5 working days. You need not answer late requests.
- A pre-tender meeting, if held, is online in e-GP. Send minutes within 5 working days to all buyers of the document, including those who did not attend.
- Change the document only by a dated, numbered Addendum in e-GP, circulated within 5 working days and posted on your website and notice boards.
- If an addendum is issued when less than one-third of the preparation time remains, extend the deadline by at least 3 working days.
- You may annul the proceedings before the deadline on justifiable grounds (Rule 48); tenders received are then returned unopened.
09Opening and Preliminary Check
e-GP opens tenders automatically after the deadline and generates the Tender Opening Report. Late tenders cannot be submitted. The TEC then works through four steps, completing the Tender Evaluation Reports that e-GP generates.
- Check the compliance, adequacy and authenticity of the qualification documents, and that every document in ITT 20 is present.
A tender is rejected at the preliminary stage if any of these is missing:
- All applicable forms, filled in and electronically signed.
- The priced schedule.
- A valid tender security.
10Technical Evaluation
- Judge responsiveness on the tender's contents only. Information you did not ask for is not considered. There is no minimum number of responsive tenders.
- A material deviation, reservation or omission makes a tender non-responsive and cannot be cured afterwards.
- Check, in order: the country-of-origin declarations in Forms 4A to 4D, conformity in Form e-PG4-5, then each qualification criterion.
- If a subcontractor is ineligible, the portion assigned to it is disallowed; you may ask for a substitute.
- You may ask a responsive tenderer to fix non-material documentary omissions, but never anything touching rates or mandatory criteria. Clarifications go through e-GP, allow at least 3 working days, and may not change the price or substance.
- Keep evaluation information confidential from tenderers and anyone not officially involved.
11Financial Evaluation
- e-GP has no arithmetic-correction step.
- Reject any tender priced more than 10% above the official cost estimate.
- Convert all currencies to Taka at Bangladesh Bank's selling rate on the opening date.
- Verify each price schedule against ITT 23, then evaluate the tender price adjusted for any equivalent-lot-value method, economic factors, unconditional discounts and, if it applies, domestic preference.
- Count only the spare parts and tools listed in the Schedule of Requirements, not those the supplier recommends.
- If the winning lot misses 20% or fewer items, buy them from the tenderer offering them at least cost. If item prices are unbalanced, the TEC may recommend raising the performance security up to 25% of the contract price.
On a tie, first look for collusion (Rule 149). Without it, prefer better past performance with the PE, then the quality more advantageous to end-users. Never use a lottery, and hold no negotiations.
12Domestic Preference
Unless the TDS turns it off, Bangladesh-made goods get a 15% margin of preference in the comparison (ITT 48 and 51).
| Group | Who qualifies |
|---|---|
| Group A | Goods made in Bangladesh where local labour, raw materials and components are more than 30% of the EXW price, and the factory has been making or assembling such goods at least since the submission date. |
| Group B | Goods made outside Bangladesh, already imported or to be imported. |
- Confirm each tender's group, reclassifying where needed. Using the wrong price form is not a reason to reject.
- Find the lowest evaluated tender in each group and compare them.
- If the lowest is from Group A, it is selected.
- If the lowest is from Group B, add 15% of each Group B tender's CIF/CIP price, for comparison only, and compare again with the lowest Group A tender. The lowest after that is selected.
Example Lowest Group A tender: Tk. 1.10 crore. Lowest Group B tender: Tk. 1.00 crore, of which the CIF/CIP price is Tk. 0.90 crore. For comparison, Group B becomes 1.00 + 15% × 0.90 = Tk. 1.135 crore, which is higher than Group A, so the Group A tender is selected. The contract is still signed at the Group A tender's own price.
13Post-qualification and Award
- Post-qualify the lowest evaluated tenderer on its submitted evidence. Any visit to its premises is a general visual inspection only, with no discussion of the tender.
- If it fails, move to the next lowest, but only while the evaluated costs remain acceptable. Once the remaining tenders are significantly above the estimate or market price, you may re-tender under Rule 34 with a revised document.
- After approval, issue the NOA (Form e-PG4-9) within 3 working days and before validity expires, with the price, performance security and deadlines. Quantities may vary up to the TDS percentage (max 20%).
- Within 24 hours, publish the award (Format e-PG4-B) for at least 28 days.
- Receive the 10% performance security, in the contract currencies, from an internationally reputable bank with a correspondent bank in Bangladesh (Form e-PG4-11, Rule 36(4)), and verify its authenticity. Sign the Contract Agreement (Form e-PG4-10) within the TDS deadline.
- Within 3 days of signing, publish the contract with beneficial ownership details (Format e-PG4-C) for at least 30 days; required above Tk. 10 lakh.
- Return tender securities: non-responsive ones after the evaluation report is approved; tenderers who did not agree to a validity extension at once; the three lowest after signing.
All tenders may be rejected only on HOPE's approval and for the reasons in ITT 57.2, but not if the lowest price matches the market price.
14Contract Management
- Shipping: the supplier notifies you and the insurer of each shipment; documents must reach you at least one week before the goods arrive, or the supplier bears the resulting costs.
- Acceptance: the TEAC starts within 24 hours of delivery; issue the Acceptance Certificate within 14 working days, for accepted parts only if defects are found.
- Payment: in the currencies of the tender price, within the PCC days; pay interest at the PCC rate if late.
- Taxes: if a tax rate changes by law, adjust the price, with HOPE's approval, so the supplier's net amount is unaffected; help the supplier use any available tax exemptions.
- Change orders: for specially manufactured goods, a change must improve the goods, cost nothing extra, and not prejudice losing tenderers. Grounds include emergencies, mistakes in the contract and similar circumstances. Additional items use contract unit prices or agreed market prices, and the total increase may not exceed 10% of the original contract price.
- Extensions: the supplier applies before the original date; decide within 21 days. Up to 30% by the PE; 30% to 100% needs HOPE's approval; above 100% needs the Secretary's.
- Liquidated damages: T = V × P × n, at the PCC rate per day, up to the PCC cap.
- Warranty and retention: warranty starts when the delivery chalan is accepted. If the supplier fails to fix notified defects in time, you may call on the retention money; otherwise release it after the warranty if goods are free of patent and latent defects. Extend the performance security if the warranty is extended.
- Disputes: amicable settlement, then the Adjudicator (referral within 14 days, decision within 28 days), then arbitration under the PCC rules.
15Termination Procedure
e-PG4 adds a formal procedure (GCC 44) for terminating for default, insolvency or convenience.
- Within 7 days of a report of grounds (or on your own initiative), verify them and prepare a Verified Report with the evidence.
- On your recommendation, the Head of the Purchaser issues a Notice to Terminate stating the grounds, the extent of termination, any special instructions, and asking the supplier to show cause. Attach the Verified Report.
- The supplier has 7 days to submit a verified position paper. If it does not, the Head issues a termination order.
- You may withdraw the notice before the position paper arrives if the items concerned were already delivered.
- The Head decides within a non-extendible 10 days of receiving the position paper, on the stated grounds only. A Contract Termination Review Committee may assist.
- Default grounds: late delivery, not maintaining a security, other breach, corrupt practice, maximum LD, or subcontracting after signing. Buy the remainder elsewhere and recover extra cost at the PCC percentage.
- Convenience (21 days' notice): conditions changed so the contract is no longer feasible, implementation impractical or unnecessary, funding withheld or reduced, or similar. Goods delivered or ready within 21 days are accepted at contract prices.
16Publishing Checklist
- International competition is justified and the method is OTM.
- Final destination, CIP/CIF named place or port, any other INCOTERM, and the foreign currency are stated.
- Domestic preference is set to "shall" or "shall not".
- Experience, capacity and liquid-asset thresholds are set per lot; subcontracting percentage stated.
- Validity, a rounded tender security in Taka or US dollar equivalent, spare parts and after-sales service requirements are filled in.
- Performance security and signing deadlines match the estimated-cost band.
- Schedule of Requirements gives earliest and latest delivery dates; specifications follow Rule 38.
- PCC shipping documents, payment terms, insurance, LD rate (0.03% to 0.05% per day) and arbitration rules are filled in.
Bidorix can review your TDS, PCC, price schedules and evaluation setup before you publish.
17Common Questions
Which exchange rate do we use?
Bangladesh Bank's selling rate on the date of tender opening, for evaluation and comparison only. Payments are made in the currencies in which the tender price is expressed.
Does domestic preference change the contract price?
No. The 15% is added to Group B prices for comparison only. The winner is paid its own tendered price.
Is there an SLT lower limit like in e-PG3?
No. e-PG4 has no SLT clause. It does keep the rule that a tender more than 10% above the official cost estimate is rejected.
Can a foreign bank issue the performance security?
Yes, if it is an internationally reputable bank with a correspondent bank in Bangladesh that makes the guarantee enforceable (Rule 36(4)). The tender security, by contrast, is a bank guarantee from a scheduled bank of Bangladesh or an e-GP tender security.
Can we pay an advance on a GoB-funded package?
Not normally. The PCC guidance says advance payments do not apply to 100% GoB-funded procurement unless the Government specifically decides otherwise; they may apply to aid-funded procurement.