e-PG5A (International) · Turnkey Plant & Equipment · For Tenderers

e-PG5A International Plant Supply and Installation Participation Guideline

How your firm or joint venture tenders on e-GP to design, supply, install and commission plant and equipment under BPPA's e-PG5A (International): who can take part, what goes in the technical and financial offers, how to price the seven schedules, how you are evaluated, and how you reach Operational Acceptance and get paid.

Based on e-PG5A (International), December 2025 (preliminary working draft) · Last reviewed 13 October 2026

Submission Checklist All STD Guides

Preparing the tender instead? Read the e-PG5A International preparation guideline.

At a glance

  • You take single responsibility for a working facility, not just equipment.
  • Technical and financial offers in one submission; your price is opened only if you are technically responsive.
  • JV allowed; subcontracting within the TDS limit, declared up front.
  • No arithmetic correction: check every rate before you submit.
  • Final 10% of payments depends on Completion and Operational Acceptance.

For foreign and Bangladeshi EPC contractors, equipment manufacturers and joint ventures tendering through e-GP.

This is a working summary, not the official document. The tender document in e-GP for your package (especially the TDS, PCC, price schedules, PE's Requirements and Appendices), the Public Procurement Act 2006 and PPR 2025 take priority. e-PG5A is a preliminary BPPA draft with internal inconsistencies; raise them through clarification before the deadline. Example figures are illustrative.

On this page

Before you tender

01Is This Tender for You? 02Eligibility, JV and Subcontracting 03Qualification Criteria 04Site Visit, Questions and Addenda

Build the tender

05The Technical Offer 06Price the Schedules 07Tender Security and Submission

After you submit

08How You Are Evaluated 09Award and Signing

Deliver the contract

10Design, Supply and Installation 11Completion, Commissioning and Guarantees 12Getting Paid 13Changes, Claims, Termination and Disputes 14Submission Checklist 15Common Questions

01Is This Tender for You?

e-PG5A is a turnkey contract: you design the facility, manufacture or buy the plant, build the civil part, install, test and commission it, train operators, and guarantee its performance. The contract goes to the lowest evaluated responsive tender.

Method
One Stage Two Envelope, international
Value
Any
Tender security
Fixed amount, up to 3% of estimate
Performance security
10% of contract price, in BDT
Retention
Per PCC (sample 5%)
Delay damages
0.03–0.05% per day, capped

Only supplying equipment, without installation and commissioning? That is e-PG4. National competition in Taka? See e-PG5A (National).

02Eligibility, JV and Subcontracting

  • Firms from any country except those in TDS 5.1; plant not from countries in TDS 6.1. Origin is where the plant is made, not your nationality.
  • Legal capacity, membership of your home country's trade body, taxes and social security paid; not insolvent or barred.
  • Not debarred or suspended, under any name, and not restricted by a development partner.
  • No conflict of interest: no common control, subsidy or shared representative with another tenderer, and no link to the consultant that prepared the design.
  • A Bangladeshi government enterprise must show legal and financial autonomy.
  • Beneficial ownership declared, to be published if you win.

Joint venture: sign a JV agreement on a Tk. 300 non-judicial stamp, or a notarised letter of intent with the draft agreement. Partners are jointly and severally liable; the lead partner has the highest share and manages the contract and receives payments; others hold at least 25% each. Composition cannot change without the PE's approval.

Subcontracting: name each subcontractor and its share on Form e-PG5A-2c, within the TDS limit (often 15–20%). A subcontractor may appear in several tenders, but only as a subcontractor.

  • submit or join more than one tender per lot: all are rejected;
  • subcontract the whole contract, or add undisclosed subcontractors later: a fundamental breach;
  • submit alternative tenders: not allowed in e-GP.

03Qualification Criteria

CriterionEvidence
General experienceYear of registration or licensing in your home country
Specific experienceCompletion certificates from employers for similar plant contracts within the look-back period (often 60–80% of the estimate in value)
Litigation and arbitrationStatement on letterhead; pending cases treated as lost; arbitration awards within the TDS limit
Liquid assetsBank statement with 3 months' transactions, approved credit line, credit commitment letter (Form e-PG5A-8) not older than 28 days, or audited working capital
Average annual turnoverAudited statements (exchange rate at period end) or certified public-sector receipts
PersonnelPersonnel Information sheets for the Project Manager and key staff
EquipmentEquipment Information form with ownership, hire or lease evidence

Example: checking the turnover test For a Tk. 60 crore, 24-month contract with F = 1.2, the PE asks for AACT of (60 ÷ 2) × 1.2 = Tk. 36 crore. In a JV, the total must reach Tk. 36 crore, the lead at least 40% (Tk. 14.4 crore) and each other partner 25% (Tk. 9 crore).

04Site Visit, Questions and Addenda

  • Visit the site at your own cost and risk, after telling the PE. You are deemed to have priced conditions you could have seen or read in the site data.
  • Buy the e-TD through an e-GP member bank by the day before the deadline.
  • Send questions through e-GP before the IFT cut-off; answers come within 5 working days. The online pre-tender meeting is optional.
  • Acknowledge every addendum. If you miss one, tell the PE before two-thirds of the tender period has passed.
  • Ask about inconsistencies in the draft STD now (taxes, retention, schedule numbering); after opening you cannot change your tender.

05The Technical Offer

ItemDetail
Submission letter and tenderer informationForms e-PG5A-1 and -2, e-signed, unaltered
JV and subcontractor informationForms -2b and -2c, JV agreement or letter of intent
Tender securitySee section 07
Licences and taxTrade licence, TIN, return acknowledgement, VAT/BIN (foreign firms give a written declaration); licences in TDS 23.2(o)
AffidavitsLegal capacity; not insolvent or bankrupt
Technical Proposal (Form -4)Site organisation, method statement, mobilisation and construction schedules, plant, safety plan, personnel, equipment, proposed subcontractors and manufacturers, time schedule, functional guarantee values
Specifications compliance (Form -5)Make, model, country of origin and full specification for every item and service
Conformity evidenceBrochures, drawings, data; spare parts and tools list; commentary against the specification
Manufacturer's authorisation (Form -6)If the TDS requires it and you are not the manufacturer

Standards in the specification are descriptive. You may offer equivalents, but you must prove they are substantially equivalent or better. State your functional guarantee values carefully: they become contract figures.

06Price the Schedules

ScheduleWhat you price
1 Plant from abroadCIP named place or CIF port in foreign currency; country of origin; Bangladesh duties shown separately
2 Local plantEXW price plus sales tax in BDT
3 DesignLocal and foreign currency portions
4 Civil worksUnit rates, including all construction materials
5 Installation and servicesLocal transport, insurance, labour, equipment, temporary works, O&M, manuals, training
6 Grand summaryTotals carried to the financial submission letter
7 Recommended sparesPriced separately; not evaluated
  • Single responsibility: anything needed for a working facility is included; unpriced items are deemed covered by other rates.
  • Local costs in BDT; foreign costs in the TDS currency. Taxes in force 28 days before the deadline are included (check how the PE resolved GCC 65.2).
  • Fixed-price tender: do not add an adjustment formula, or you are rejected. Adjustable tender: give the index sources asked for in the Appendix to the Tender.
  • Offer discounts only unconditionally, and for multiple lots say how they apply.
  • Avoid front-loading: unbalanced rates can raise your performance security to 25%.

Example: currency effect At an illustrative Tk. 122 per USD, USD 3.4 million of imported plant is Tk. 41.48 crore in the comparison. The TEC uses the Bangladesh Bank selling rate on the opening date, so exchange-rate risk after that is yours unless prices are adjustable.

07Tender Security and Submission

  • Tender security for the TDS amount (BDT or USD equivalent): bank draft, pay order, guarantee of a Bangladeshi scheduled bank (Form e-PG5A-7), or a guarantee from an internationally reputable bank endorsed by its correspondent bank in Bangladesh. Valid 28 days beyond tender validity.
  • Submit both offers together in one e-GP submission before the deadline; allow time for large files. No late tenders.
  • Modify, substitute (with a new security) or withdraw only before the deadline.
  • Files must be readable and virus-free.

The security is forfeited if you withdraw within validity, fail to give performance security, refuse to sign, or engage in corrupt practice. The three lowest securities are held until the contract is signed.

08How You Are Evaluated

  1. Technical offers open first. Missing forms, priced schedule or security mean rejection.
  2. The TEC checks eligibility, qualifications, the Technical Proposal and specification compliance. Material deviations cannot be fixed later.
  3. Reply to clarifications within the time given (at least 3 working days), without changing substance.
  4. Only technically responsive financial offers are decrypted, after HOPE approves.
  5. No arithmetic correction; prices converted to BDT; discounts and economic factors (late completion, mandatory spares, life-cycle costs) added for comparison.
  6. Lowest evaluated tender is post-qualified; the TEC may inspect your facilities.

Example: completion time counts B's Tk. 59.98 crore tender offers completion 20 days late. With a 0.05% per day factor, Tk. 0.60 crore is added for comparison, giving Tk. 60.58 crore: still below A's Tk. 61.04 crore, so B wins, but at its own price and committed to the time it offered.

09Award and Signing

  1. NOA within 3 working days of approval; it binds you.
  2. Performance security, 10% of the contract price in BDT (Form e-PG5A-11 or draft/pay order), within 7/10/14 working days by contract size, valid 28 days beyond the Intended Completion Date.
  3. Sign within 14/21/28 days.
  4. Advance payment security (Form -12) within 28 days, if you take the advance.
  5. Your beneficial ownership is published with the contract.

Unsuccessful? Ask for a debriefing; complain and appeal under Sections 29–30 of the PPA 2006 and Rules 72–77 of PPR 2025.

10Design, Supply and Installation

  • Name your Contractor's Representative within 14 days and a Construction Manager on site; send the organisation chart (21 days) and detailed programme (28 days); report monthly.
  • Submit Appendix 7 documents; the Project Manager approves within 14 days or they are deemed approved. You remain responsible for your design either way.
  • Procure, ship, clear customs and transport the plant; notify each shipment. Customs delays not your fault earn extension.
  • You carry care and risk until Completion even though ownership of imported plant passes on loading.
  • Take out cargo, installation all-risks, third-party, vehicle and workers' insurance with the PE co-insured.
  • Respect site regulations, labour laws, safety, child labour rules and the environment; appoint an accident prevention officer.
  • Subcontractors not named in the contract need prior written approval.

11Completion, Commissioning and Guarantees

  1. Notify mechanical completion. The PE supplies operators and utilities within 7 days; you pre-commission.
  2. Completion Certificate within 14 days, or a defect list; silence or PE use means deemed Completion. Risk passes to the PE.
  3. Commission and run the Guarantee Test within the PCC period. If the PE cannot let you test, the guarantees are deemed met.
  4. Request the Operational Acceptance Certificate; it is due within 7 days or deemed issued.
  • Below guarantee but above the minimum (usually 95% of capacity or 105% of consumption): fix it or pay the Appendix 8 LD per 1%, capped (up to 10%).
  • Below the minimum: you must fix it at your cost.
  • Delay damages: 0.03–0.05% per day on uncompleted work, capped; a bonus may apply for early completion.
  • Defect liability: 540 days from Completion or 1 year from Operational Acceptance, whichever is first; longer for listed critical components. Start remedial work within 15 days of notice or the PE may do it at your cost.

Example A plant guaranteed at 50,000 m³/day tests at 48,500 (97%). At an LD rate of Tk. 20 lakh per 1%, you either upgrade the plant and retest or pay Tk. 60 lakh. At 46,000 (92%) you have no choice: you must fix it.

12Getting Paid

Appendix 1 sample terms; payments due within 45 days of invoice or documents.
ScheduleAdvanceMainCompletionOp. Acceptance
Imported plant10%80% on shipment documents5%5%
Local plant10%80% on delivery to carrier5%5%
Design10%90% on design acceptance
Installation10%80% monthly measured5%5%
  • Advance guarantee reduces as plant is delivered or work paid; no interest on the advance.
  • Retention (PCC, sample 5%) comes back after the Defects Correction Certificate.
  • Performance security halves at Operational Acceptance and is returned within 7 days of final payment.
  • Late payment earns interest at the PCC rate; if a certified payment is unpaid for 84 days you may terminate, and after 14 days' notice you may suspend or slow work.
  • Price adjustment, if any, uses the Appendix 2 formula on each certificate, excluding the advance and contractor-caused delay.
  • A change in tax law adjusts the price so your net receipt is unaffected (with HOPE approval).

13Changes, Claims, Termination and Disputes

  • Changes: give an estimate of the cost of preparing a Change Proposal first; you are reimbursed if the PE drops a change it requested. You may object if total changes exceed 15% of the price. Proceed on a Pending Agreement Change Order if price is not agreed.
  • Claims: notice within 28 days of the event and full details within 42 days, or you lose the claim.
  • Extensions: the PE decides within 21 days; above 30% needs HOPE, above 100% the Secretary.
  • Notice to Correct: reply within 5 days with your remedy plan.
  • Termination for default: a Notice of Default gives you 21 days to explain or remedy; grounds include stopping work 28 days, failing to start, letting security lapse, LD cap reached, unauthorised subcontracting.
  • Disputes: Adjudicator within 14 days (decision in 28, you pay fees and the PE reimburses half), then arbitration: for foreign contractors under UNCITRAL or ICC rules as the PCC chooses.

14Submission Checklist

  • Eligible; no conflict of interest; one tender per lot.
  • JV agreement or notarised letter of intent; shares and lead partner set.
  • Subcontractors and manufacturers named within the limit.
  • Experience, turnover, liquid asset, litigation, personnel and equipment evidence complete.
  • Licences, tax documents, affidavits and manufacturer's authorisation attached.
  • Technical Proposal and compliance sheet complete; functional guarantee values stated.
  • All seven schedules priced in the right currencies and INCOTERMs; no unbalanced rates; checked twice for errors.
  • Tender security valid 28 days beyond validity.
  • Submitted early, acknowledgement saved.
Tendering for a turnkey plant contract?

Bidorix can review your qualification evidence, technical proposal and price schedules before you submit.

Request Assistance Ask a Question

15Common Questions

Can a foreign manufacturer and a local civil contractor tender together?

Yes, as a JV (each liable for the whole contract), or the manufacturer can lead and name the local firm as a subcontractor within the TDS limit.

If I made a mistake in a rate, will the PE correct it?

No. e-GP has no arithmetic correction, and the price cannot change after opening. Check before submission.

Do I include VAT and customs duties?

ITT 26.18 says all taxes are in the price, but GCC 65.2 says the PE pays duties and VAT on plant. Ask the PE to confirm through clarification before you price.

Are recommended spare parts used to decide the winner?

No. Schedule 7 is not evaluated, though mandatory spares and any TDS spare-parts factor are.

The PE's site was not ready for pre-commissioning. What am I entitled to?

More time without LD, release of payments against a bank guarantee, reimbursement of security extensions and care costs, and extra compensation if the delay exceeds 180 days.

Can I get a bonus for finishing early?

Only if PCC 44.3 sets one; it is usually equal to the LD rate and capped.