e-PG5A National Plant Supply and Installation Preparation Guideline

How to tender, evaluate and manage a turnkey contract in which one contractor designs, supplies, installs, tests and commissions plant and equipment, such as a substation, a pumping station, a water treatment plant, a generator set or a lift system, through national competition using BPPA's e-PG5A (National) and the one-stage two-envelope method.

Based on e-PG5A (National), May 2026 · Last reviewed 13 October 2026

Publishing Checklist All STD Guides

Tendering instead? Read the e-PG5A National participation guideline.

At a glance

  • One contractor, single responsibility: design, plant, civil part, installation, commissioning.
  • Everything priced and paid in BDT; no foreign currency or INCOTERMs.
  • Financial offers stay encrypted until the technical report is approved.
  • A statistical check rejects significantly low-priced tenders.
  • Tender security up to 3%; performance security 10%; retention 10%.

For Procuring Entity officials, project managers, Tender Evaluation Committee members and Approving Authorities buying plant through national competition.

This is a working summary, not the official document. The STD in e-GP, the Public Procurement Act 2006 and PPR 2025 take priority. Section 1 (ITT) and Section 3 (GCC) must not be altered; tailor only the TDS, PCC, Price Schedules, PE's Requirements, Drawings and Appendices. The May 2026 text still has inconsistencies (section 16). Figures in the examples are illustrative.

On this page

Before you start

01When to Use e-PG5A National 02What You Prepare 03Key Time Limits

Prepare the tender

04Qualification Criteria 05Other TDS Entries 06Price Schedules and Taxes 07PE's Requirements and Appendices 08Fill In the PCC

Evaluate and award

09Opening and Technical Evaluation 10Financial Evaluation and Low-Price Check 11Award, Securities and Signing

Run the contract

12Design, Supply and Installation 13Completion, Commissioning and Guarantees 14Payments and Price Adjustment 15Changes, Delays and Termination 16Points to Correct in the STD 17Publishing Checklist 18Common Questions

01When to Use e-PG5A National

Use e-PG5A (National) when you need plant and equipment designed, supplied, installed and commissioned as a working facility by one contractor (a turnkey contract combining goods, works and services), and national competition in Taka is enough. Award goes to the lowest evaluated responsive tender, for any value.

Nature
Plant and equipment, turnkey
Method
One Stage Two Envelope (OSTETM)
Competition
National
Value
Any
Currency
BDT only
Joint venture
Allowed
How the National version differs from e-PG5A (International).
TopicNationalInternational
Prices and paymentBDT onlyBDT plus a foreign currency
Imported plantNo CIP/CIF schedule; plant priced delivered, taxes includedSeparate schedule on CIP or CIF terms
Price schedulesSix: plant, design, civil works, installation, grand summary, recommended sparesSeven
Low-price checkSignificantly low-priced tender test with weighted average and NPPINot in that STD
Single responsive tenderRejected if more than 20% away from the official estimateNo such rule
ArbitrationArbitration Act 2001, place in the PCCUNCITRAL or ICC rules for foreign contractors

Need foreign manufacturers to compete in their own currency? Use e-PG5A (International). Only buying equipment without installation? Use e-PG3. For mainly civil construction, use a works STD.

02What You Prepare

SectionYour job
1. Instructions to Tenderers (ITT)Do not change.
2. Tender Data Sheet (TDS)Fill every entry (sections 04–05).
3. General Conditions of Contract (GCC)Do not change.
4. Particular Conditions of Contract (PCC)Fill every entry; leave none blank (section 08).
5. Tender and Contract FormsForms e-PG5A-1 to -8 for tenderers (submission letter, information sheets, price schedules, technical proposal, compliance sheet, manufacturer's authorisation, tender security, credit line); -9 to -14 for the contract (NOA, agreement, securities, amendment).
6. Price schedulesSet up the item lists for each schedule (section 06).
7. PE's RequirementsScope, technical specifications under Rule 38, certificate forms, change-order procedure and forms (section 07).
8. DrawingsDated, numbered drawings and site plans.
Appendix to the Tender and contract Appendices 1–8Price adjustment data, payment terms, insurance, time schedule, approved subcontractors, PE's scope, documents for approval, functional guarantees.

03Key Time Limits

StepTime limit
Answer clarification requests5 working days, through e-GP
Pre-tender meeting minutes; addendum circulation5 working days each
Deadline extension after a late addendumAt least 3 working days if under one-third of the time remains
Tenderer's reply to a clarificationAt least 3 working days
Notice of rejection of all tenders3 working days after HOPE's decision
NOA after approval3 working days, within validity
Publish awardWithin 24 hours, kept for 28 days
Performance security (Rule 123(7))7 / 10 / 14 working days (estimate up to Tk. 5 crore / up to Tk. 25 crore / above)
Sign contract14 / 21 / 28 days by the same bands
Publish contract and beneficial ownershipWithin 3 days of signing, kept 30 days
Advance payment securityWithin 28 days of award
Contractor's organisation chart; programme21 days; 28 days from the Effective Date
Project Manager's approval of design documents14 days, or deemed approved
Extension of time decision21 days from the contractor's notice

04Qualification Criteria

All criteria are pass/fail. Failing any one makes the tender non-responsive.

TDSCriterionSTD guidance
13.1(a)Years of general experience as contractor, subcontractor or management contractor3 or 5 years, counted back from IFT publication
13.1(b)Number of similar contracts, look-back period and minimum valueOften 1 contract in 5–10 years; value 60–80% of the estimate
14.1(a)Maximum arbitration awards against the tenderer3 in the last 5 years
14.1(b)Liquid assets, credit line or working capitalBDT amount
14.1(c)Average annual turnover (AACT)Formula below; best 3 of 5 or best 5 of 10 years
15.1Project Manager, engineers and key staffTotal and similar experience in years
16.1Major equipment owned, hired or leasedType and minimum number

AACT = (E ÷ N) × F, where E = official estimate, N = contract duration in years (at least 1), F = 1.0 to 1.5 (lower for larger contracts).

Example: setting the financial criteria A 33/11 kV substation is estimated at Tk. 20 crore over 18 months (1.5 years). Annual cash flow is 20 ÷ 1.5 = Tk. 13.33 crore. With F = 1.2, ask for average annual turnover of Tk. 16 crore. One similar contract of 60–80% of the estimate means Tk. 12–16 crore. (The STD's own example: Tk. 24 crore over 18 months gives Tk. 16 crore a year, and with F = 1.5 an AACT of Tk. 24 crore.)

Joint ventures (TDS 17.1–17.2): agreement on a Tk. 300 non-judicial stamp (Format e-PG5A-E), or a notarised letter of intent with the draft agreement. State the maximum number of partners. The STD's suggested split:

CriterionJV totalLead partnerEach other partner
General experienceNot summedFull TDS figureSame as lead
Specific experience100% (different contracts summed)At least one contractNone
Liquid assets, turnover100%40%25%
Personnel, equipment100%NoneNone
Business share100%HighestAt least 25%

The STD notes that the Rules do not allow JVs for goods, but allows them here because a turnkey contract combines goods, works and services.

05Other TDS Entries

TDSWhat to enterSTD guidance
1.1PE, tender name, reference, lotsLots identified as in the PE's Requirements
3.1, 3.3Source of funds; development partner
5.1, 6.1Ineligible countries for tenderers and for plant
18.1Maximum subcontractingUp to 20% of contract value recommended
18.4Nominated subcontractors and their componentsOr "none"
19.1Single lot or lot-by-lot
23.2(o)Required licencese.g. ABC/BC/C Electrical Supervisory Licence, gas company category 1.1–1.5 licences, or "none"
23.2(e)iiIncome tax assessment yearImmediate past AY
23.2(r), 23.3(c)Extra technical and financial documents
26.3Single responsibility for everything, or named components, plus items the PE provides
26.7(c)Named place of final destination for local transport
26.8Fixed or adjustable prices, and the methodAdjustment normal above 18 months (GCC 67.1)
29.3(b)Spare parts required; expected operating period
30.1Extra content for the Technical Proposal
31.1(c), (g)Years of litigation history and audited statementsMatch the general experience years
31.1(e)Manufacturer's authorisation: none, all items, or listed itemsNot usually needed for off-the-shelf goods
32.2Validity60–150 days
34.1Tender security in BDT and beneficiaryFixed amount, not over 3% of the estimate
54.6Economic factors: delay adjustment % per day and cut-off; high-usage spares and period; life-cycle factors (fuel, productivity)Delete those not used
64.1Performance security 10%; working days7/10/14 by estimate
64.3Security deposit for a government enterprise10% deducted from invoices
68.1, 68.3Retention 10%; contractual security cap 10%These conflict; see section 16
69.2Days to sign14/21/28
72.1Proposed Adjudicator, hourly fee, expenses, biography

Example: tender security and timelines On a Tk. 20 crore estimate, 3% is Tk. 60 lakh, so state a fixed amount no higher, for example Tk. 50 lakh. Because the estimate is between Tk. 5 crore and Tk. 25 crore, the winner has 10 working days for the performance security and 21 days to sign.

06Price Schedules and Taxes

Schedule (ITT 26.6)Content
1Plant and mandatory spare parts, with country of origin; prices include VAT, AIT and other levies
2Design services
3Civil works part, unit rates, including all construction materials
4Installation and other services: local transport to the final destination, insurance, labour, equipment, temporary works, O&M, manuals, training
5Grand summary of Schedules 1–4
6Recommended spare parts, priced separately; not used in evaluation
  • Tenderers quote on a single-responsibility basis: anything reasonably inferable is included, and unpriced items are deemed covered elsewhere.
  • Plant in Schedule 1 excludes construction materials; those go in the civil or installation schedules.
  • All taxes, customs duties, VAT and levies in force 28 days before the deadline are included in rates (ITT 26.17). GCC 65.2 still says the PE pays customs and VAT on Schedule 1 plant; decide which applies and say so (section 16).
  • Unconditional discounts and multi-lot discounts are allowed; alternatives are not.
  • Fixed-price tender: an adjustable quote is non-responsive. Adjustable-price tender: a fixed quote is accepted with zero adjustment.

The Schedule 5 form in Section 5 still shows the International layout (plant from abroad, plant from Bangladesh, design, installation) and omits civil works. Rebuild it as Schedules 1–4 above so e-GP totals every schedule.

07PE's Requirements and Appendices

  • Scope of supply and installation: exactly what the contractor delivers, and the interfaces with other contractors.
  • Technical specifications under Rule 38: new, current-model equipment; national or international standards; required inspections and tests and where they happen; functional performance. Standards are descriptive: tenderers may offer equivalents.
  • Forms: Completion Certificate, Operational Acceptance Certificate, and the change-order forms (request, estimate, acceptance, proposal, change order, pending-agreement order, application).
Appendix to the TenderIndex descriptions, base values and sources (BBS by default) and the weighting table for price adjustment.
Appendix 1Terms and procedures of payment (section 14).
Appendix 2Price adjustment formula and coefficients, or a statement that prices are firm.
Appendix 3Insurances: cargo, installation all risks, third party, vehicles, workers, and any the PE takes out.
Appendix 4Time schedule in weeks or months from the Effective Date.
Appendix 5Major items needing approval and approved subcontractors and manufacturers.
Appendix 6What the PE provides: personnel, facilities, works, supplies, utilities for commissioning, and any charges.
Appendix 7Documents for approval and for review.
Appendix 8Functional guarantees, test preconditions, minimum levels (95% capacity, 105% consumption), liquidated damages and cap.

Appendix 6 matters: if your operators, utilities or raw materials are not ready for pre-commissioning, the contractor gets time and costs (GCC 43.5). Plan them as carefully as the plant.

08Fill In the PCC

GCCEntrySTD guidance
1.1(ll), (mm), (qq), (tt)PE, Project Manager, contractor, site and drawings
2.6Sectional completion datesIf any
3.1, 7.1(k)Notice addresses; other contract documents
9.1, 9.2, 16.1Ineligible countries; nominated subcontractors
18.1Site possession datesNormally within 28 days of signing
27.3Spare parts supply periodSample clause: ex-stock consumables, others within 6 months
28.1, 29.1Commencement and Time for CompletionFrom the Effective Date
43.2.2Period to complete the Guarantee TestDays after Completion
44.3Early completion bonus and maximumOr "Not Applicable"; usually equal to LD
45.2, 45.10Defect liability; extended liability for critical componentsExtended period up to 5 years
48.1(b)Liability cap multiplier
52.1Insurance covers and deductiblesWorks and plant 110% of value; equipment 110% of replacement; other property 10% of price; deductibles 3–5%
60.2, 60.4Price adjustment or not; coefficientsA + B = 1
61.1Contract price; advance payment and dateAdvance up to 10%, against a bank guarantee
61.5Interest on late paymentCommercial rate, or "None"
63.1, 63.4Performance security %; reduction at Operational AcceptanceChoose one of the two 63.4 options
64.1Retention10%
68.1LD rate and cap0.03–0.05% per day; cap up to 10%
80.1(k)Extra compensation eventsOr "none"
82.2, 82.3Adjudicator; place of arbitrationIEB President appoints the Adjudicator if parties disagree

09Opening and Technical Evaluation

  1. e-GP opens only technical offers after the deadline and generates the Tender Opening Report. Financial offers stay encrypted.
  2. Preliminary examination: all forms filled and e-signed, priced schedule present, valid tender security. Any missing means rejection.
  3. Technical examination: country of origin, Technical Proposal (Form e-PG5A-4), qualification evidence, compliance with the PE's Requirements without material deviation, and the specifications compliance sheet (Form e-PG5A-5).
  4. Material deviations, reservations or omissions cannot be cured. Non-material documentary gaps may be filled on request, but never anything touching price or mandatory criteria. Information not asked for is ignored.
  5. Clarifications through e-GP, signed by the TEC Chair only, with at least 3 working days to reply.
  6. The TEC sends the technical report directly to HOPE or the Authorized Officer.

There is no minimum number of responsive tenders. Validity may be extended at most twice, and only for tenders that passed the preliminary examination; the tender security must then run 28 days past the new date.

10Financial Evaluation and Low-Price Check

  1. After approval, e-GP decrypts financial offers of technically responsive tenderers only.
  2. No arithmetic correction is made in e-GP.
  3. Apply discounts and the TDS 54.6 economic factors: delay adjustment, mandatory spares and service, life-cycle costs. Recommended spares are not counted.
  4. Significantly low-priced tender (SLT) check on all responsive prices (ITT 55), described below.
  5. Rank. Ties: check for collusion (Rule 149), then superior past performance with the PE, then the quality end-users find more advantageous. Never a lottery.
  6. If prices are unbalanced, the TEC may recommend a performance security of up to 25%.
  7. Post-qualify the lowest; a visit to its facilities is allowed, without discussing the tender. If it fails, go to the next.

Weighted average x̄ = 0.5 × (average of quoted prices) + 0.2 × official estimate + 0.3 × XNPPI. Standard deviation Sd = √(Σ(x̄ − xi)² ÷ n). Any tender below x̄ − Sd is rejected.

XNPPI is the official estimate multiplied by the National Public Procurement Price Index: the average deviation between estimate and award in goods contracts awarded through e-GP in the 28 days up to tender opening (excluding national limited tendering).

Example: estimate Tk. 20.00 crore; recent awards averaged 8% below estimate, so XNPPI = Tk. 18.40 crore.
StepWorkingResult
Responsive pricesA 19.00, B 18.20, C 15.00Average 17.40
Weighted average0.5 × 17.40 + 0.2 × 20.00 + 0.3 × 18.4018.22
Standard deviation√((0.78² + 0.02² + 3.22²) ÷ 3)1.91
Lower limit18.22 − 1.9116.31
OutcomeC (15.00) is below the limit and rejectedB lowest at Tk. 18.20 crore

Only one technically responsive tender? The formula is not used. Compare its evaluated price with the official estimate: more than 20% away, it is non-responsive; within 20%, it may be recommended. On a Tk. 20 crore estimate the band is Tk. 16–24 crore.

Reject all tenders, with HOPE approval, only if the lowest exceeds a realistic estimate, competition was ineffective, no one can meet a reasonable time, all are non-responsive, the documents are defective, or misconduct is proven; never if the lowest matches the market.

11Award, Securities and Signing

  1. Issue the NOA (Form e-PG5A-9) within 3 working days of approval, before validity expires, with the draft contract (Form e-PG5A-10).
  2. Publish the award (Format e-PG5A-B) within 24 hours, for 28 days.
  3. Performance security: 10% of the contract price, in BDT, by bank draft, pay order or bank guarantee (Form e-PG5A-11), within 7/10/14 working days.
  4. Sign within 14/21/28 days. Failure to give security or sign forfeits the tender security; award to the next.
  5. A government enterprise gives a 10% security deposit deducted from invoices instead.
  6. Publish the contract (Format e-PG5A-C) and beneficial ownership (above Tk. 10 lakh) within 3 days, for 30 days.
  7. Return the other tender securities: non-responsive ones within 28 days after approval; the three lowest after the contract is signed.

Example: the security cap problem B's Tk. 18.20 crore contract needs a performance security of Tk. 1.82 crore. Retention at 10% adds up to another Tk. 1.82 crore, so the total reaches 20%, while TDS 68.3 caps contractual security at 10% (Tk. 1.82 crore). State in the TDS how you apply the cap, or the TEC's recommendation under Rule 36(2) to exceed it.

12Design, Supply and Installation

  • Appoint the Project Manager within 14 days of the Effective Date if not named. All instructions and certificates come through the Project Manager.
  • The contractor appoints its Representative (deemed approved if you do not object within 14 days) and a Construction Manager on site.
  • Within 21 days: organisation chart with key staff CVs. Within 28 days: detailed programme. Then monthly progress reports.
  • Design approval: review Appendix 7 documents within 14 days, or they are deemed approved. Disapprove only for non-compliance or bad engineering practice.
  • Hand over site possession by the PCC dates; late possession is a compensation event.
  • Ownership of plant passes when it arrives on site; care and risk stay with the contractor until Completion.
  • Attend factory and site tests at your own travel cost; extra tests you order are paid if they pass.
  • Check insurances and site regulations; you are co-insured on most policies.

13Completion, Commissioning and Guarantees

  1. The contractor notifies mechanical completion. Within 7 days you supply operators, utilities and materials for pre-commissioning.
  2. The Project Manager issues the Completion Certificate within 14 days, or lists defects (7 days on each repeat). Silence, or your use of the facility, means deemed Completion. Care and risk then pass to you.
  3. Commissioning and the Guarantee Test follow, within the PCC period. If the test cannot be done for reasons not the contractor's fault, the guarantees are deemed met.
  4. On request, the Project Manager issues the Operational Acceptance Certificate within 7 days, or it is deemed issued.
Example: a pumping station guaranteed at 2,000 m³/hour; LD Tk. 5 lakh per 1% shortfall (illustrative), cap 10% of contract price.
Test resultOutcome
2,000 or moreGuarantee met
1,940 (97%)Above the 95% minimum: contractor either fixes it or pays 3 × Tk. 5 lakh = Tk. 15 lakh, then gets Operational Acceptance
1,880 (94%)Below 95%: contractor must modify the plant at its own cost and retest; failing that, consider termination
  • Liquidated damages for delay: 0.03–0.05% per day of the value of uncompleted work, capped at up to 10%. Reaching the cap is grounds for termination.
  • Defect liability: 540 days from Completion or 1 year from Operational Acceptance, whichever is first, extended for downtime; optional extended liability for critical components up to 5 years.
  • Liability cap: the contract price times the PCC multiplier, excluding defective equipment and patent indemnity.

Example: delay damages and defect period Uncompleted work worth Tk. 4 crore finishes 20 days late at 0.05% a day: 4 crore × 0.0005 × 20 = Tk. 4 lakh, far below a 10% cap of Tk. 1.82 crore. If Completion is 1 March 2027 and Operational Acceptance 1 June 2027, defect liability ends on 1 June 2028 (one year after acceptance), which comes before the 540-day date in late August 2028.

14Payments and Price Adjustment

Appendix 1 sample terms (payments within 45 days of invoice). Different terms need written approval.
ScheduleAdvanceMain paymentCompletionOperational Acceptance
Plant10%80% on delivery to the carrier, with the documents you name5%5%
Design10%90% on design acceptance
Installation and services10%80% of monthly measured value5%5%

Example: Tk. 10 crore of plant Tk. 1 crore advance against a guarantee; Tk. 8 crore on delivery documents; Tk. 50 lakh at Completion; Tk. 50 lakh at Operational Acceptance.

  • The advance payment security reduces as plant is delivered or work paid. Write the civil works payment terms yourself: Appendix 1 has no schedule for them.
  • Retention (10%) is held until the Defects Correction Certificate.
  • The performance security halves at Operational Acceptance (unless the PCC says otherwise) and expires 540 days after Completion or 365 days after Operational Acceptance, whichever is first; it is returned within 7 days of final payment.
  • A change in tax rates adjusts the price, with HOPE approval, so the contractor's net amount is unchanged.
  • Late payment carries interest at the PCC rate.

P = A + b(Lₘ/L₀) + c(Sₘ/S₀) + …, with A the fixed part and the weights summing to 1. Indexes from the Bangladesh Bureau of Statistics unless stated; base values 28 days before the deadline; adjustment date the mid-point of manufacture or installation.

Example: price adjustment Normal only when the contract period exceeds 18 months, so the 18-month substation above would be fixed-price. On a longer contract with A = 0.15, labour 0.30 (index 100 → 108), steel 0.35 (100 → 115) and miscellaneous 0.20 (100 → 104): P = 0.15 + 0.324 + 0.4025 + 0.208 = 1.0845. A Tk. 2 crore certificate becomes Tk. 2.169 crore (+Tk. 16.9 lakh). No adjustment on the advance, and no increase for delays caused by the contractor.

15Changes, Delays and Termination

  • Changes: Request for Change Proposal → contractor's estimate of preparation cost → your acceptance → Change Proposal → Change Order within 14 days of agreement. If price is not agreed, issue a Pending Agreement Change Order. The contractor may object if all changes together exceed 15% of the price.
  • Extensions: decide within 21 days; up to 30% of contract time by the PE, 30–100% with HOPE, beyond 100% with the Secretary.
  • Claims: notice within 28 days of the event and full details within 42 days, or the claim is lost.
  • Suspension: if you suspend for more than 90 days without contractor fault, it may demand resumption within 28 days. It may suspend or slow work after 14 days' notice of non-payment.
  • Termination for default: Notice to Correct first (reply in 5 days); then a Notice of Default with 21 days to explain; then termination with HOPE approval, with 14 working days' notice. Grounds include stopping work for 28 days, failing to start, no security, LD cap reached, unauthorised subcontracting, corrupt practice; for the contractor, site not handed over within 84 days or certified payment unpaid for 84 days. HOPE may set up a Contract Termination Review Committee.
  • Also insolvency, convenience (21 days' notice), and force majeure (notice within 14 days).
  • Disputes: amicable settlement; Adjudicator within 14 days (decision in 28, fees shared); arbitration after 28 days under the Arbitration Act 2001 at the PCC place.

Example: extension authority On an 18-month contract you may extend by up to 5.4 months; up to 18 more months needs HOPE; anything beyond needs the Secretary.

16Points to Correct in the STD

The May 2026 text reuses goods, works and International templates. Settle these in the TDS and PCC, or ask BPPA:

  • Taxes: ITT 26.7(a) and 26.17 put VAT, AIT and customs duty in the price, but GCC 65.2 says the PE pays customs on Schedule 1 plant and VAT on plant.
  • Security cap: performance security 10% plus retention 10% (TDS 68.1, PCC 64.1) against a 10% contractual security cap (TDS 68.3). PCC 64.1 also says 10% "of the contract price" rather than of each payment; TDS 68.1 starts retention on "delivery of Goods and acceptance by the TEAC".
  • Retention guarantee: Form e-PG5A-13 talks of releasing the first half of retention at take-over, which the GCC never provides.
  • Price adjustment: PCC 60.4 puts A at 0.20–0.25 and cites ITT 27.8/27.9; Appendix 2 puts A at 0.10–0.15 and skips condition (b).
  • Schedule numbering: ITT 26.6 makes installation Schedule 4, but ITT 26.7(c) calls it Schedule 3; the Grand Summary form lists "plant from abroad" and "plant from within the country" and omits civil works; columns say "carry Columns 6 and 7".
  • Form numbers: the guidance notes number forms differently from Section 5 (manufacturer's authorisation 5 or 6, tender security 6 or 7, NOA 7 or 9, performance security 9 or 11); the Functional Guarantee form cites "ITT 24(n)", which does not exist.
  • Section numbers: two sections are headed "Section 7" (PE's Requirements and Drawings); PE's Requirements is numbered 6.1–6.6; ITT 1.1 and 26.13 point to a "Section 6: Schedule of Requirements" that contains only price forms; the change-order log cites a non-existent Annex 8; the GCC table of contents shows "Error! Bookmark not defined".
  • Defect liability and performance security: GCC 45.2 fixes 540 days or 1 year, but PCC 45.2 asks for months; PCC 45.3 holds an unrelated "late programme" amount; PCC 63.4 gives two contradictory options and cites GCC 42.10 (it is 45.10); ITT 66.1 says the security runs 28 days past the Intended Completion Date, the submission letter says past the Completion Certificate, and GCC 63.4 runs it into the defect period.
  • Commencement: GCC 28.1 repeats the completion text of 29.1.
  • Arithmetic errors: ITT 53.1 says e-GP makes no corrections, yet ITT 38.1(b), 52.2 and the tender security form still refer to accepting corrections.
  • Cross-references: e.g. ITT 4.5 cites GCC 38; ITT 47.2 cites 23.2(n), (d), (o), (p); ITT 54.2(b) cites 23.10–23.11; ITT 56.1 cites Clause 52; GCC 36 cites 39.2.1; 37.3 cites 31.2; 41.7 "referred to an 82.3"; 42.4 cites 39.4; 46.2 cites 69.2.2 for termination; 47.2 cites 34.1; 50.2 cites GCC 17 for insurance; 52.6 cites 51.1 and 49.4; 54.3 cites 65; 69.1.3 cites 64.1.1; 70.2(c) cites 44 for suspension; 70.4 cites 65.1–65.2; 71.3 cites 43.1; 73.2 cites 72.1; PCC 68.1 says GCC 71.1.
  • Goods wording: ITT 2.1(g), 13.1 and 31.1 speak of "supply of Goods"; the SLT price index uses the goods category; the Acceptance Certificate covers "Goods" and construction defects.
  • Signing rule: TDS 69.2 cites Rule 123(9); the NOA cites Rule 123(11).
  • JV table: cites "ITT 14.1(d)", which does not exist.
  • Assessment year: TDS 23.2(e)ii says "immediate past" but its example for FY 2025-26 is AY 2023-24.
  • Garbled text: ITT 19.1 repeats a sentence; GCC 70.6 is incomplete; GCC 70.1 refers to a delivery period "in the TDS" that the TDS lacks; reporting formats read "FUNDING NEGRMATION" and skip item 12; every page header reads "e-PG5APW3".

17Publishing Checklist

  • Turnkey scope confirmed; national OSTETM chosen; estimate realistic (it drives the SLT check and the single-tender 20% rule).
  • Qualification: experience, arbitration, liquid assets, AACT, personnel, equipment, JV split and licences set.
  • Subcontracting limit and nominated subcontractors stated.
  • Price schedules set up with one consistent numbering, including civil works in the grand summary; fixed or adjustable choice stated.
  • Tax treatment decided (ITT 26.17 vs GCC 65.2) and stated.
  • Economic factors in TDS 54.6 filled or deleted.
  • Specifications, tests, drawings and functional guarantees with minimum levels complete.
  • Appendices 1–8 complete, especially PE's supplies for commissioning and civil works payment terms.
  • PCC complete: dates, Guarantee Test period, LD, bonus, defect liability, insurance, advance, interest, retention and security cap reconciled, adjudicator, arbitration place.
  • Validity, tender security and timelines set by estimate band.
Preparing a turnkey plant tender?

Bidorix can check your TDS, PCC, price schedules and guarantees before you publish.

Request Assistance Ask a Question

18Common Questions

National or International: which version should we use?

National when local contractors and suppliers can deliver and you want prices only in Taka. International when you need foreign manufacturers or EPC firms to tender in their own currency on CIP or CIF terms.

Can we open the financial offers together with the technical offers?

No. e-GP opens technical offers first; financial offers are decrypted only for technically responsive tenderers after HOPE approves the technical report.

A tender is much cheaper than the others. Must we accept it?

Not if it falls below the weighted average minus one standard deviation: it is then a significantly low-priced tender and is rejected as financially non-responsive.

Only one tender passed the technical evaluation. Can we award?

Yes, if its evaluated price is within 20% of the official estimate and it passes post-qualification. More than 20% away, it is non-responsive.

What if our operators are not ready for commissioning?

The contractor gets more time without LD, released payments against a bank guarantee, and reimbursement of security extension and care costs; beyond 180 days, extra compensation is agreed.

Are recommended spare parts used to decide the winner?

No. Only mandatory spares and the TDS 54.6 spare-parts factor count; Schedule 6 recommended spares are not evaluated.