e-PG9 Direct Procurement Goods Preparation Guideline
How to invite a single supplier, negotiate, award and manage a goods contract under the Direct Procurement Method, using BPPA's Standard e-Tender Document e-PG9 and the Public Procurement Rules 2025.
Invited as the supplier? Read the e-PG9 participation guideline.
This is a working summary, not the official document. The e-PG9 STD issued by BPPA (a December 2025 draft copy), the Public Procurement Act 2006 and PPR 2025 take priority. e-PG9 does not itself list the grounds for direct procurement: confirm and record that PPR 2025 permits the Direct Procurement Method for your package before you invite anyone.
01When to Use e-PG9
Use e-PG9 when the Procuring Entity (the Purchaser) wants to select only one supplier for goods and related services under the Direct Procurement Method (DPM). Instead of an open tender, you send one supplier an invitation, receive its offer, negotiate and sign.
- Nature
- Goods and related services
- Method
- Direct Procurement (DPM)
- Competition
- None: one invited supplier
- Value
- Any value, where DPM is permitted
- Award basis
- Satisfactory negotiation
- Currency
- Bangladesh Taka
| Topic | e-PG3 (open tender) | e-PG9 (direct) |
|---|---|---|
| Who is invited | Anyone, by public advertisement | One named supplier, by letter |
| Rules for the process | Full ITT and TDS | 16-paragraph invitation letter |
| Tender security | Required | Not required |
| Evaluation | TEC, lowest evaluated responsive tender | Check of the single offer, then negotiation |
| Negotiation | Not allowed | Expected; minutes become a contract document |
| Liquidated damages | Per day | Per week or part of a week |
02How the Document Works
e-PG9 is short. You fill in the bracketed items, delete the italic guidance notes, and remove rows marked "if applicable" that you do not need.
| Part | What it contains |
|---|---|
| Invitation Letter and Instruction to Tenderer | Eligibility, conflict of interest, manufacturer's authorisation, performance security, validity, pricing, clarifications, submission, negotiation and award. You upload it. |
| Annex 1: PE's Requirements | Technical Specifications and Compliance form, Price and Delivery Schedules for goods and for related services, specification summary, optional Drawings, and Inspection and Tests. |
| Annex 2: Offer Forms | Supplier's Offer Form and Manufacturer's Authorisation Letter. |
| Contract Agreement and Conditions of Contract | The agreement and 35 Conditions of Contract (CC), many with blanks for you to fill. |
| Contract forms | Notification of Award, Bank Guarantee for Performance Security, Bank Guarantee for Advance Payment, Sample Letter of Invitation for Negotiations. |
| Formats | Public Reporting on Contract Signing, and Acceptance Certificate. |
Once signed, the Contract Agreement prevails over every other document. The rest are read in this order:
- Minutes of Negotiations
- The Supplier's offer
- Conditions of Contract
- PE's Requirements (Schedule of Requirements and Technical Specifications)
- Completed schedules, including Price Schedules
- Any other document listed as part of the Contract
03Key Time Limits
| Step | Time limit | Reference |
|---|---|---|
| Clarification requests | Before the date and time you set | Para 11 |
| Supplier submits its offer | Within the days you set; may be the same day in an emergency | Para 12 |
| Issue the NOA | Within 3 working days of award approval | Para 15, CC 15.1 |
| Send the draft contract | At the same time as the NOA | CC 16.1 |
| Performance security | Working days set under Rule 123(7), stated in the NOA | NOA |
| Sign the contract | Days set under Rule 123(11), stated in the NOA | NOA |
| Publish contract signing | Within 3 days of signing; display for at least 30 days | Para 16, CC 17.1 |
| Supplier's claim on a change order | Within 28 days of receiving the order | CC 12.2 |
| Start acceptance inspection | TEAC within 24 hours of delivery | CC 14.2 |
| Acceptance | Within 14 working days of receipt at final destination | CC 14.1 |
| Decide a delivery extension request | Within 21 days of the supplier's notice | CC 28.2 |
| Claim on the security | Breach or unpaid amount continuing 14 days or more after notice | CC 23.2 |
| Return performance security | Within 7 days of final payment, after the Acceptance Certificate | CC 23.7 |
| Refer a dispute to the Adjudicator | Within 14 days of the first written correspondence | CC 34 (31.2) |
| Terminate for corrupt practice | After 14 days' notice | CC 5.3 |
04Fill In the Invitation Letter
| Para | What to state | Guidance in e-PG9 |
|---|---|---|
| Header | Direct Contracting reference number and date; supplier and its representative | Use the same reference on every later letter. |
| 1, 2 | PE, project or grant, contract title, implementing agency | Add "and the Related Services" if services are included. |
| 4.1 | Eligible countries | Name them. Goods must originate in eligible countries. |
| 7 | Manufacturer's Authorisation | Keep it if the supplier may not be the manufacturer; otherwise insert "Not Applicable" after careful consideration. |
| 8 | Performance Security | Always required, per the Conditions of Contract. |
| 9 | Validity of offer | The supplier states it; check it covers negotiation and approval. |
| 11 | Name and e-mail of the PE's representative; last date and time for clarifications | Written requests only. |
| 12, 13 | Days allowed for the offer; submission address and attention | Can be the same day if, given an emergency, negotiations have already started. |
| 14 | Negotiation arrangements | The STD notes negotiation is expected to be virtual in the circumstances. |
| Signature | Name and title of the PE's signatory | Signed on behalf of the PE. |
Before sending, check the supplier is not disqualified by a conflict of interest (para 6). It has one if it or an affiliate:
- helped prepare the design or specifications of these goods as a consultant;
- has been, or is proposed to be, hired by the PE to implement the contract;
- would supply goods, works or services resulting from consulting services it or a controlled affiliate provided for this project; or
- has a close business or family tie with PE staff involved in the invitation, specifications, evaluation, or implementation and supervision, unless resolved to the PE's satisfaction.
A state-owned enterprise may be invited only if it shows it is legally and financially autonomous, operates under commercial law, and is not a dependent agency of the PE (para 5).
05Annex 1: PE's Requirements
- Technical Specifications and Compliance form: for each item, fill in the item number, name, detailed specification and standards required, and the inspections or tests required with the test place. The supplier fills in country of origin, make and model or brand, and the specification offered.
- Rule 38: prepare specifications under Rule 38 of PPR 2025. State the national or international standards, require new, unused, current-model goods, and say what inspections and tests you need and where.
- Same item numbers in the price schedule and the specification form.
- Price and Delivery Schedules: one for goods (point of delivery, delivery period in days) and one for related services (point and period of completion). Prices are in Taka, in figures and words. No credit is given for early completion.
- Specification summary: optional table (1.3.1) plus detailed specifications (1.3.2) where necessary. Cover standards, related services, tests and inspections, and functional guarantees under the warranty.
- Drawings: optional; insert "the following" or "no" drawings and list them with number, name and purpose.
- Inspection, Examination and Tests: list each test with its nature, frequency, location and procedure, and name any inspection agency you use with its scope of services (see CC 25).
06Fill In the Conditions of Contract
The CC have no separate PCC: fill the blanks directly and delete all italic text before signing.
| CC | What to state | Guidance in e-PG9 |
|---|---|---|
| 2 | PE's legal name, country, project site or final destination | Full location details. |
| 3 | Notice addresses for both parties | Officer, title, unit, address and e-mail. Notices go by the quickest method, such as e-mail with proof of receipt. |
| 6.1 | Documents the supplier must furnish | For example insurance certificate, warranty certificate, inspection certificate, factory shipping details. |
| 12.1(c) | Maximum % increase and decrease in quantities | Insert both percentages. |
| 13.2 | Packing, marking and documentation | Or refer to the Technical Specifications. |
| 19.1 | Transport responsibility | Default: supplier transports to the final destination, with insurance and storage, included in the price. Or state other agreed trade terms. |
| 20.1(i) | Advance payment % and days after signing | Paid on a claim; needs the Advance Payment bank guarantee. |
| 20.1(ii) | % on delivery and acceptance, and days to pay | Paid after the documents and the Acceptance Certificate. |
| 21.1 | Insurance | Coverage, currency and amount. |
| 26.3 | Warranty period | Minimum 3 months for supplies and 1 year for equipment. Shelf-life may be used as the warranty period. |
| 26.7, 26.9 | Days to repair or replace; warranty destination | Insert both. |
| 27 | Delivery date; completion date of services | Give a phased schedule if partial deliveries are allowed; delete 27.2 if there are no services. |
| 29.1 | LD rate per week and maximum % | Of the price of delayed goods or unperformed services; cap as % of the contract price. |
| 35 | Additional clauses | Add as needed, otherwise delete the row. |
Example: liquidated damages per week Suppose CC 29.1 sets 0.5% per week (an illustrative rate, not one from the STD) and goods worth Tk. 8 lakh arrive 10 days late. Ten days is one week plus part of a second week, so two weeks count: 2 × 0.5% × Tk. 8,00,000 = Tk. 8,000. Once the total reaches the CC cap, you may terminate under CC 33.
07Securities and Retention
- Tender security
- Not required
- Performance security
- 10% of the contract price
- Retention
- 10% of payments, until warranty expiry
- Contractual security
- 10% of the contract value
- Form: Bank Draft, Pay Order or irrevocable unconditional Bank Guarantee in the STD format, without alteration, from a scheduled bank of Bangladesh acceptable to you.
- Verify it by writing to the issuing bank branch.
- Claims: you may claim if the supplier is in breach, or has not paid an amount due, for 14 days or more after notice. If compensation due equals or exceeds the security, call the full amount. Notify the supplier of any claim.
- Return within 7 days of the final payment, subject to the Acceptance Certificate.
- Government supplier: the performance security may be kept as the contractual security instead of retention money until the warranty expires.
- Release retention only after the warranty, if the goods are free of patent defects (obvious, like a pen that does not write) and latent defects (hidden, like a pen that writes 0.75 km instead of 1.5 km) and all conditions are met.
CC 23.1 sets the contractual security at 10% of the contract value, while CC 23.4 and 23.9 add a 10% performance security and 10% retention. Agree how these fit together during negotiation and record it in the minutes.
08Receive and Check the Offer
The supplier replies with Annex 2. Check that it contains:
- The Supplier's Offer Form, signed, with the invitation reference and date.
- Declarations on conformity, eligibility and no conflict of interest.
- The suspension and debarment statement for the right source of funds: GoB (PEs and development partners) or development partner (World Bank Group and cross-debarment).
- The professional misconduct certificate under Rule 149 (GoB) or the fraud and corruption certificate (development partner).
- A stated validity period and the commitment to provide a performance security.
- The completed compliance form and priced schedules, with a grand summary.
- A Manufacturer's Authorisation on the manufacturer's letterhead, if you required one.
The offer form confirms you may accept or reject the offer and may annul the direct contracting process at any time before award.
09Negotiation, Award and Publication
- Invite the supplier to negotiate using the Sample Letter of Invitation for Negotiations, with the logistics, date and time.
- Negotiate price, delivery, securities, payment and any open CC points. Sign Minutes of Negotiations; they rank first among the contract documents.
- Conclude the contract only if negotiations end satisfactorily (para 14), and obtain approval from the Approving Authority.
- Within 3 working days of approval, issue the NOA with the contract price, the performance security amount and deadline, and the signing deadline. Send the draft Contract Agreement and all contract documents with it.
- Receive and verify the performance security, then sign the Contract Agreement. The supplier may start supplying only after both are done.
- Within 3 days of signing, publish the contract information on your notice board or website, and on the BPPA website or portal with beneficial ownership details. Keep it posted for at least 30 days.
Beneficial ownership Required for any contract above Tk. 10 lakh: the names and NIDs of the owners, partners, CEO or MD, directors and shareholders holding 10% of issued shares. State-owned enterprises are excused.
The NOA form refers to "CC Clause No 16" for the performance security and "ITT Clause 23" for signing. e-PG9 has no ITT 23, and the security is in CC 23. Correct these references when you issue the NOA.
10Contract Management
- Acceptance: the TEAC starts within 24 hours of delivery; process acceptance within 14 working days. If defects are found, certify only the accepted parts.
- Inspection: tests are at the supplier's cost. Your attendance is at your own cost. You may order extra tests and reject goods that fail; the supplier rectifies or replaces them and retests at no cost.
- Price: fixed. Taxes are the supplier's responsibility, but if a tax rate changes by law, adjust the price, with HOPE's approval, so the supplier's net amount is unchanged.
- Change orders: you may change specifications of specially made goods, shipment or packing, quantities within the CC range, the delivery place, extra tests, or related services. Make an equitable adjustment and amend the contract in writing.
- Extensions: the supplier must apply before the original delivery date. Decide within 21 days; extensions on justifiable grounds carry no LD. Up to 30% by the PE; over 30% up to 100% needs HOPE or an authorised officer; over 100% needs the Secretary.
- Warranty: starts when you accept the delivery chalan; earlier deliveries expire earlier. If the supplier does not fix a notified defect in time, remedy it at the supplier's risk and expense.
- Liability: capped at the total contract price, except criminal negligence, wilful misconduct, repair or replacement of defective equipment, and patent indemnity.
11Termination and Disputes
- Default: late delivery, failure of any other obligation, or professional misconduct. Buy the undelivered goods elsewhere; the supplier pays the extra cost and continues any part not terminated.
- Insolvency: terminate without compensation once a court finally declares the supplier bankrupt or insolvent.
- Convenience: by notice, at any time. Goods ready for shipment within 21 days are accepted at contract prices; for the rest, have them completed or cancel and pay an agreed amount.
- Force majeure: if performance is blocked for more than 60 days at once or 120 days in total, try to agree a solution; failing that, either party may terminate.
- Disputes: settle amicably first, then refer to the Adjudicator within 14 days of the first written correspondence. Foreign supplier: final settlement under the Arbitration Act 2001. National supplier: adjudication or arbitration under Bangladesh law.
12Issuing Checklist
- The DPM justification is recorded and approved under PPR 2025.
- The supplier has no conflict of interest; an SOE meets the autonomy test.
- Reference, eligible countries, clarification contact and deadline, offer deadline and address are filled in.
- Manufacturer's Authorisation kept or marked "Not Applicable".
- Specifications follow Rule 38, with matching item numbers in the price schedules.
- Tests, inspection agency and drawings (if any) are listed.
- CC blanks filled: site, notices, documents, quantity range, packing, transport, payment, insurance, warranty, delivery, LD rate and cap.
- All italic guidance text is deleted.
Bidorix can review your invitation letter, requirements and Conditions of Contract before you send them.
13Common Questions
Do we need a tender security?
No. e-PG9 does not ask for one. The supplier commits in its offer to provide a performance security if awarded.
Can the offer be submitted on the same day?
Yes. Paragraph 12 lets you set the number of days, and says it may even be the same day if, given an emergency, negotiations have already started.
Which document wins if the minutes and the offer disagree?
The Contract Agreement prevails over everything. After it, the Minutes of Negotiations come first, ahead of the supplier's offer and the Conditions of Contract.
Can we pay an advance?
Yes, if you fill in CC 20.1(i) with the percentage and days. The supplier must give an advance payment guarantee from a scheduled bank of Bangladesh in the STD format.
Can we cancel after receiving the offer?
Yes. You may accept or reject the offer, and annul the direct contracting process at any time before the contract is awarded.