e-PS6 · Consulting Firm · For Procuring Entities

e-PS6 Consulting Firm Simple Time Based Preparation Guideline

How to invite short-listed consulting firms, evaluate their technical and financial proposals, negotiate and manage a time-based contract for intellectual and professional services up to Tk. 1 crore, where you pay for staff time actually spent, using BPPA's Standard Request for Proposal e-PS6 and the Public Procurement Rules 2025.

Based on e-PS6, December 2025 · Last reviewed 12 October 2026

Issuing Checklist All STD Guides

Short-listed as a firm? Read the e-PS6 participation guideline.

At a glance

  • Consulting firms short-listed after an EOI, for assignments up to Tk. 1 crore.
  • Technical and financial proposals; financials stay encrypted until the technical evaluation is approved.
  • Technical pass mark 70 of 100; QCBS weights normally T 0.8–0.9, F 0.1–0.2.
  • Pay staff-month rates for time actually spent, plus reimbursables, up to a ceiling; rates are not negotiable.
  • Itemized statements each period, paid within 14 days; you must supervise closely.

For Procuring Entity officials, Proposal Evaluation Committee (PEC) members and Approving Authorities buying consulting services from firms.

This is a working summary, not the official document. BPPA marks the December 2025 e-PS6 as a preliminary working draft and asks PEs to contact BPPA if anything is unclear. The STD, the Public Procurement Act 2006 (Sections 37–38) and PPR 2025 (Rules 124–148) take priority over this page.

On this page

Before you start

01When to Use e-PS6 02How the Document Works 03Key Time Limits

Prepare the RFP

04Fill In the Proposal Data Sheet 05Set the Technical Criteria 06Write the Terms of Reference 07Fill In the PCC

Select the firm

08Clarifications and Pre-Proposal Meeting 09Technical Evaluation 10Financial Opening and Scoring 11Negotiation 12Award, Security and Signing

After signing

13Payments and Supervision 14Termination and Disputes 15Points to Correct in the Draft 16Issuing Checklist 17Common Questions

01When to Use e-PS6

Use e-PS6 after an Expression of Interest has produced a short-list, when you want a consulting firm paid for the time its staff actually spend, and the estimated cost is up to Tk. 1 crore. BPPA recommends a time-based contract when:

  • the scope of services cannot be set with enough precision;
  • the duration and quantity of services depend on things outside the consultant's control; or
  • the output you need is hard to assess.

It requires you to supervise the firm closely and be involved in the day-to-day work.

Nature
Service
Who can propose
Short-listed firms only
Value
Up to Tk. 1 crore
Contract
Time based, up to a ceiling
Selection
As set in the PDS: QCBS, FBS, LCS etc.
Currency
Bangladesh Taka
Selection is the same as e-PS5; the contract and payments differ.
Topice-PS5 lump sume-PS6 time based
Best whenScope and outputs clearly definedScope, duration or output uncertain
What you pay forAccepted outputs, as fixed percentagesStaff time actually spent × agreed rates, plus actual reimbursables
Contract priceFixed, all-inclusive lump sumCeiling not to be exceeded
BillingInvoice within 15 days of each output; paid in 30 daysItemized statement within 7 days of each period; paid in 14 days
Rate breakdowns (5B2, 5B3)Only for additional servicesThe basis of every payment
Extra contract terms—Working hours, overtime and leave; counterpart personnel
Your effortJudge the outputsClose, day-to-day supervision

e-PS6, suitably tailored, may also be used for Single Source Selection. Above Tk. 1 crore, use the e-PS8 complex time-based guideline. Hiring one individual instead of a firm? See e-PS4.

02How the Document Works

PartWhat it containsYour role
Letter of InvitationNames of the short-listed firms; the invitation cannot be transferred.Fill in
1. ITC61 clauses on eligibility, conflict of interest, preparation, submission, evaluation and award.Do not alter
2. PDSAssignment-specific data, numbered like the ITC.Fill in
3. GCC75 General Conditions of Contract.Do not alter
4. PCCContract-specific data, numbered like the GCC.Fill in
5. FormsTechnical forms 5A1–5A8, financial forms 5B1–5B4, Contract Agreement, Appendices 1–7.Firm fills
6. TORObjectives, scope, deliverables, inputs from you.Write
Formats P–VJV agreement, LOA, award and signing reports, commencement letter, amendment, accomplishment certificate.Use when applicable

Once signed, the contract documents rank in this order:

  1. Contract Agreement
  2. Particular Conditions of Contract (PCC)
  3. General Conditions of Contract (GCC)
  4. Appendices: Description of Services, Reporting, Key Personnel, Client's facilities, Cost Estimates, advance payment and performance security guarantees
  5. Any other document listed in the PCC

03Key Time Limits

StepTime limitReference
Firms ask for clarificationBefore two-thirds of the preparation time has passedITC 15.1
You answer through e-GPWithin 5 working days, to all firmsITC 15.3
Pre-proposal meeting minutesWithin 7 days of the meetingITC 16.3
Proposal validitySet in the PDS, normally 60–150 daysPDS 30.1
Ask for validity extensionAt least 10 days before expiryITC 31.1
Financial openingUsually at least 1 week after notifying passing firmsITC 42.1
Notice of rejectionWithin 7 days of the decisionITC 52.1
Issue the LOAWithin 3 working days of approvalITC 53.1
Publish contract awardWithin 24 hours of the LOA; display 28 daysITC 56.1
Publish contract signingWithin 3 days of signing; display 30 daysITC 58.1
Start of servicesDays set in the PCC, no later than 21 days from the Effective DatePCC 18.1
Consultant notifies a variationWithin 7 days of becoming awareGCC 21.3
Itemized statementWithin 7 days after each month, or each PCC intervalGCC 53.1
Pay a statementWithin 14 days of receipt; interest if more than 30 days lateGCC 53.2, 53.3
Final report deemed approved60 days after receipt unless you notify deficienciesGCC 56.1
Release performance securityWithin 28 days of completionGCC 58.4
Termination for defaultAt least 21 days' noticeGCC 64.1

04Fill In the Proposal Data Sheet

ITCWhat to stateGuidance in e-PS6
1.1Client, services, selection methodFor example QCBS, FBS or LCS.
1.2Phasing and completion periodEach phase must be satisfactory before the next starts. Describe any downstream work and how it affects evaluation.
3.1, 3.3Source of funds; development partnerDP payments follow the financing agreement.
7.1Countries whose materials and supplies are not allowedName them.
21.1(d)Other documents requiredList them.
23.5Stamp value for the JV agreementTk. 300 non-judicial stamp.
23.12Estimated professional staff-monthsQCBS only. Do not disclose the budget. On a time-based contract this estimate also shapes the ceiling, so make it realistic.
23.13Available budget, excluding taxesFBS only. Do not give staff-months.
23.14Minimum qualification and experience of key staffState per position.
24.1(i), (j)Whether training is a component; extra technical informationDelete what does not apply.
25.1Reimbursable expenses allowedSample list: office, travel, communication, equipment, report printing, training, subcontracts, allowances, other. Delete what does not apply.
28.1(a)Services and facilities you provideDefine clearly.
29.1CurrencyTaka. Another currency only for inputs from abroad, converted at the Bangladesh Bank selling rate on the opening date.
30.1Validity daysNormally 60–150, by complexity.
41.2Criteria, sub-criteria and pointsSee the next section.
41.4Minimum technical pointsFixed at 70.
45.1Weights T and FT normally 0.8–0.9, F 0.1–0.2; check Rule 139(24)(b) and (e).
46.2Negotiation addressInsert it.
54.1Performance security %, or "Not Applicable"3–5% where deliverables are time-critical or feed downstream work (Section 62(2) PPA, Rules 36(9), 147(2)).
60.1Start date and locationInsert both.

05Set the Technical Criteria

Allocate 100 points across four criteria. Sub-criteria are optional.

CriterionUsual pointsSub-criteria
(i) Firm's specific experience5–10Relevant past assignments.
(ii) Work plan and methodology20–40Methodology, work plan, organization and staffing.
(iii) Key professional staff40–60Points per position (Team Leader first), each split: general qualifications 15–25%, adequacy for the assignment 50–60%, time with the firm 10–15%, region and language 10–15%.
(iv) Transfer of knowledge0–20Relevance 20–30%, approach 30–50%, qualifications of trainers 20–35%.
Total100Pass mark 70.

Example: scoring a Team Leader worth 20 points With weights 20% / 55% / 15% / 10%, the sub-maximums are 4, 11, 3 and 2 points. A Team Leader rated 100% on qualifications, 80% on adequacy, 100% on time with the firm and 50% on region and language scores 4 + 8.8 + 3 + 1 = 16.8 of 20.

06Write the Terms of Reference

The TOR is the key document of the RFP. A clear TOR reduces ambiguity in proposals, negotiation and delivery. It normally contains:

  • Background of the project.
  • Objectives of the assignment.
  • Scope of services: activities, tasks and expected results.
  • Transfer of knowledge (training), when appropriate.
  • List of reports, delivery schedule and period of performance.
  • Data, facilities and local services you will provide.
  • Institutional arrangements.

Hand all firms any information that gave one of them a head start, for example from earlier related work (ITC 12). Provide project data and reports with the RFP, and help firms get data from other departments (ITC 28.1).

07Fill In the PCC

GCCWhat to stateGuidance in e-PS6
1.1, 3.1, 12.1Parties, notice addresses, authorized representativesA JV's contact comes from the Lead Partner.
2.1Phases, or "None"
6.1(e), 8.1, 11.1Extra contract documents, non-eligible countries, Lead PartnerState "none" where not used.
17.1Effectiveness conditionsFor example advance payment and its guarantee, or "none".
18.1, 19.1, 20.1Days to commence, contract period, expiryCommencement no later than 21 days from the Effective Date.
33.4(a)Months after completion for notifying claimsSuggested 3–6 months.
33.4(b)Liability ceilingNot less than total estimated payments, or the insurance proceeds, whichever is higher.
36.1(c)Other actions needing your approvalFor works supervision, add acting as "Engineer" under the works contract.
38.3Restrictions on future use of documents and softwareChoose one of the three sample options, or "none".
40.1(d)Other assistance you give
47.1Consultant's bank accountSubstantiated by the bank, authenticated by you.
49.1Contract price (the ceiling)Payments cannot exceed it except by agreed variation or GCC 46.3 additions.
52.1, 52.2Advance %, days, guarantee validity, amortizationUsually 10%, the recommended maximum, against a bank guarantee. The PCC sample releases the guarantee when payments reach 60% of the price.
53.1Statement intervalMonthly, bimonthly or quarterly.
53.3Interest on late paymentUsually the prevailing commercial lending rate, or delete.
75.2(b)Place of arbitration

Also complete the appendices that time-based contracts lean on:

  • Appendix 3: key personnel, job descriptions, minimum qualifications and staff-months for each. Leave is included in these staff-months.
  • Appendix 4: services and facilities you provide, and working hours and holidays for key personnel. No paid overtime, sick or vacation leave unless stated here.
  • Appendix 5: monthly rates for personnel and the reimbursable items.
  • Counterpart personnel (GCC 44), if you will provide your own staff to work under the firm's direction.

Example: building the ceiling Team Leader 6 staff-months × Tk. 3,00,000 = Tk. 18 lakh; two specialists 8 staff-months each × Tk. 2,00,000 = Tk. 32 lakh; support staff Tk. 6 lakh; reimbursables Tk. 14 lakh. Ceiling Tk. 70 lakh. You pay only for time actually spent, so the final bill may be lower, but never higher without an approved variation. (Illustrative rates.)

08Clarifications and Pre-Proposal Meeting

  • Clarifications: answer requests made before two-thirds of the preparation time has passed, through e-GP within 5 working days, and send the answer to all short-listed firms without naming the source.
  • Pre-proposal meeting: optional, held online through e-GP on the date in the notice. Send minutes, with questions and answers, within 7 days.
  • Addendum: the only way to change the RFP, before the deadline, through e-GP. Extend the deadline if firms need time to respond.

09Technical Evaluation

  1. Technical proposals open automatically on e-GP after the deadline. Financial proposals stay encrypted.
  2. Check eligibility and look for any new conflict of interest since short-listing. Ask the firm to remove a conflict, or treat the proposal as non-responsive. Hiding a conflict means non-responsive.
  3. Reject a JV or sub-consultancy between two short-listed firms, and one with a non-short-listed applicant unless you approved it before the deadline.
  4. Each PEC member scores every proposal separately against the PDS criteria. A firm's points are the average of all members, including the Chair.
  5. Proposals below 70 points are non-responsive.
  6. Get the technical evaluation approved, including prior review where needed, before anyone sees a financial proposal.
  • Only the PEC Chair sends clarification requests, through e-GP. They must not change the substance, key staff or make a non-responsive proposal responsive.
  • A technical proposal that contains financial information may be treated as non-responsive.
  • One CV per position; a key expert offered in two proposals for this assignment breaches ITC 23.15.

10Financial Opening and Scoring

  • Notify passing firms through e-GP of the opening date, usually at least 1 week ahead. Tell the others their financial proposals will be returned unopened.
  • The PEC opens financial proposals publicly; firm names, technical points and prices are read out and recorded. Attendees sign an attendance sheet. Give minutes on request.
  • e-GP has no arithmetic correction. Do not seek financial clarifications.
  • Activities not priced are treated as included elsewhere. If quantities differ from the technical proposal, do not adjust the price.
  • Exclude all taxes from evaluation; they are settled at negotiation.

Under QCBS, the lowest price gets 100 financial points and others are scaled:

Fp = 100 × Fm ÷ F    Cs = Tp × T + Fp × F

Example: QCBS with T = 0.8, F = 0.2 Firm A: Tp 85, price Tk. 80 lakh. Firm B: Tp 78, price Tk. 64 lakh. Fp for B = 100, for A = 100 × 64 ÷ 80 = 80. Cs for A = 68 + 16 = 84; for B = 62.4 + 20 = 82.4. Firm A ranks first despite the higher price. Firm C, with Tp 68, failed the technical stage and its price was never opened.

Under FBS, select the highest technical score whose evaluated price is within the PDS budget (excluding taxes). Any price above the budget is non-responsive.

11Negotiation

  1. Invite the top firm (highest Cs under QCBS, highest technical within budget under FBS) to the PDS address. It must first confirm all key staff are available.
  2. Start from the PEC's comments and the approving authority's recommendations.
  3. Technical: methodology, work plan, activity schedule, staffing, training and your facilities. These become the Description of Services. You may require a key expert found unfit to be replaced.
  4. Financial: fine-tune for agreed technical changes only. Unit rates for remuneration and reimbursables cannot be negotiated. Clarify tax liabilities and add them to the contract price.
  5. Allow staff substitution only for undue delay, death or medical incapacity, with equal or better qualifications. If key staff were offered without confirming availability, the firm may be disqualified.
  6. Sign minutes and initial the draft contract. If talks fail, move to the next firm, never negotiating with two at once.

You may reject all proposals if they have major deficiencies, prices are substantially above budget and cannot be bridged, or professional misconduct is established under Chapter Seven of PPR 2025. Notify all firms within 7 days.

12Award, Security and Signing

  1. Within 3 working days of approval, with no complaint pending and within validity, issue the Letter of Acceptance (Format Q) with the price, any performance security, and the signing deadline.
  2. Within 24 hours, publish the award (Format R) on your notice board or website and the BPPA website, for 28 days.
  3. Collect the performance security, if required, in the working days set under Rule 123(7): pay order, bank draft or unconditional bank guarantee (Appendix 7) from a scheduled bank, valid 28 days beyond completion. Verify it with the bank.
  4. Sign within the days set under Rule 123(11). All JV partners sign.
  5. Within 3 days, publish signing (Format S), with beneficial ownership on the BPPA portal for contracts above Tk. 10 lakh, for 30 days.
  6. Notify technically responsive unsuccessful firms, return unopened financial proposals, and debrief on request about the firm's own proposal only.
  7. Send the commencement letter (Format T) once conditions are met; this sets the Effective Date.

Example: performance security At 5% on Tk. 80 lakh the security is Tk. 4 lakh. You may claim on it if a notified breach or unpaid amount continues for 14 days or more, and must release it within 28 days of completion.

13Payments and Supervision

  • Remuneration: staff time actually spent from the start date, at the agreed rates. Rates cover salaries and allowances, social charges and overhead, and the firm's fee. Part months are paid per calendar day at 1/30 of the monthly rate.
  • Reimbursables: those actually and reasonably incurred, as the contract provides.
  • Statements: within 7 days after each month (or PCC interval), in duplicate, itemized, with invoices and vouchers, separating remuneration from reimbursables. Check the time claimed against what you supervised.
  • Payment: within 14 days of receipt; interest at the PCC rate if more than 30 days late. Correct any overpayment or underpayment in later payments.
  • Ceiling: keep a running total; payments cannot exceed it without an approved variation. Extending key staff time beyond Appendix 3 needs written agreement and the variation procedure.
  • Final payment: after the final report and final statement are approved. If you do not notify deficiencies within 60 days, they are deemed approved.
  • Suspension: by written notice stating the failure and giving up to 30 days to remedy.
  • Variations: by written agreement. Within 10% of the original price, the Approving Authority approves; above that, the next higher authority. Never beyond 30%.
  • Personnel: no changes without approval; replacements equal or better, at no higher remuneration, with the firm paying extra travel. Leave is taken within the Appendix 3 staff-months and must not delay the work.
  • Counterparts and facilities: if you cannot provide the agreed counterpart staff or Appendix 4 facilities, agree how the work proceeds and any extra payment.
  • Records: you may inspect and audit the firm's accounts for up to 5 years. All reports, data and software belong to you.

Example: a monthly statement In March the Team Leader works the full month (Tk. 3,00,000), one specialist works 12 days (Tk. 2,00,000 ÷ 30 × 12 = Tk. 80,000), and reimbursables with vouchers come to Tk. 45,000. The statement, due by 7 April, totals Tk. 4,25,000; if received on 5 April, pay by 19 April.

14Termination and Disputes

  • Default: either party, with at least 21 days' notice, for a fundamental breach: the firm not remedying a suspension, a knowingly false statement, corrupt practice, ignoring an arbitral award; or you failing to pay within 45 days of notice or to remedy a material breach within 45 days.
  • Insolvency: either party, without compensation.
  • Convenience: you, at any time, by notice stating the extent and date.
  • Force majeure: notify within 14 days; HOPE decides whether it exists. If a material part is blocked for 60 days or more, either party may terminate. Lack of funds is never force majeure.
  • On termination: pay for satisfactory services and, except for the firm's default, reasonable wind-down costs.
  • Disputes: amicable settlement; after 28 days, either party may give notice of arbitration under the Arbitration Act 2001 at the PCC location. Both keep performing and you keep paying sums due.

15Points to Correct in the Draft

The December 2025 draft carries several leftovers from the lump-sum version and broken cross-references. Fix them in your RFP or ask BPPA:

  • The guidance note says e-PS6 is for cost "above BDT 1 Crore", while the cover says "up to BDT 1 Crore". The cover matches its place in the series.
  • GCC 51.1 says payments follow "outputs", and PCC 53.1 releases the advance guarantee at 60% of the "lump-sum Contract Price". On this contract payments follow time spent; read these as the contract price.
  • GCC 46.1 says the cost estimate is in Appendix 6 (the advance payment guarantee); it is Appendix 5. GCC 44 refers to an Appendix 5B for counterparts that does not exist; list counterparts in Appendix 4 or the PCC.
  • The 5B form list names 5B2 Summary, 5B3 Remuneration, 5B4 Reimbursables, but the forms are 5B2 remuneration, 5B3 reimbursables, 5B4 summary. GCC 21.6 cites 5B3 and 5B4 for unit prices; it should be 5B2 and 5B3.
  • Form 5A1 points to "ITC 56.1" for the start date; the PDS entry is ITC 60.1. ITC 4.2 says "ITT 4.3" for ITC 4.3.
  • GCC 36.2 cites 35.1(b) for 36.1(b); GCC 46.3 cites 44.1 for 46.1; GCC 75.3 cites 57.1 for 59.1. The Appendix 6 guarantee and PCC 17.1 cite GCC 50 for the advance, which is GCC 52.
  • GCC 6.1 lists "Appendix 1 to 8"; there are 7. Appendix 7 cites PPR 2008; the commencement letter cites a GCC 33.2 on insurance (insurance is GCC 34).
  • GCC 57.1 allows 30 days to remedy a suspension, while GCC 64.2(a) treats failure within 28 days as a fundamental breach. Align them.
  • PCC 18.1, 19.1 and 20.1 do not line up with the GCC clause numbers (GCC 18.1 is the Effective Date).

16Issuing Checklist

  • EOI and short-list are complete; the estimated cost is within Tk. 1 crore; the scope really is uncertain enough for a time-based contract.
  • Letter of Invitation lists only short-listed firms.
  • PDS: method, staff-months (QCBS) or budget (FBS), key staff minimums, reimbursables, validity, criteria totalling 100, pass mark 70, T and F, performance security decision.
  • TOR covers objectives, scope, reports and schedule, your inputs and institutional arrangements.
  • PCC: parties, effectiveness, timings, liability, ceiling, advance, statement interval, interest, arbitration place; Appendices 3–5 ready.
  • Information that could give one firm an advantage is shared with all.
  • Lump-sum leftovers and cross-references corrected; italic guidance removed; ITC and GCC unchanged.
Preparing a consultancy RFP?

Bidorix can review your PDS, evaluation criteria, TOR and PCC before you issue them.

Request Assistance Ask a Question

17Common Questions

Can we negotiate the firm's staff-month rates down?

No. Under QCBS and FBS, unit rates for remuneration and reimbursables cannot be negotiated. You can agree changes to inputs and staffing, which change the ceiling.

Do we pay the full ceiling?

No. You pay for time actually spent and reimbursables actually incurred, as shown in itemized statements. The ceiling is the most you can pay without an approved variation.

Are staff paid for leave and overtime?

Only as Appendix 4 allows. Otherwise the rates are deemed to cover them, and any leave sits inside the Appendix 3 staff-months.

How is a part month paid?

Per calendar day spent on the assignment, each day being 1/30 of the monthly rate.

Is a performance security mandatory?

No. Set it in the PDS only where needed, typically for time-critical deliverables or those feeding later work, at 3–5% of the contract price.

When should we choose e-PS5 instead?

When you can define the scope and outputs clearly and want to pay a fixed price against accepted reports. See the e-PS5 guideline.