e-PW2B Works Limited Tender Preparation Guideline
How to prepare, publish, evaluate and award a limited tender for works up to Tk. 5 crore among your enlisted contractors with BPPA's e-PW2B Standard Tender Document, then run the contract from site handover to the final account.
Submitting a tender instead? Read the e-PW2B participation guideline.
This is a working summary, not the official document. The e-PW2B STD issued by BPPA, the Public Procurement Act 2006 and PPR 2025 take priority. Use the version attached in e-GP for your package. Worked examples on this page are illustrations, not values from the document.
01When to Use e-PW2B
Use e-PW2B when the Procuring Entity will select a contractor for works through the Limited Tendering Method on e-GP, with the invitation limited to contractors holding updated, valid enlistment with the PE.
- Nature
- Works (and physical services)
- Method
- Limited Tendering (LTM)
- Value limit
- Up to Tk. 5 crore
- Contract type
- Admeasurement (unit rates)
- Who can tender
- PE-enlisted contractors
- Award basis
- Lowest evaluated; e-lottery on a tie
e-PW2B looks like e-PW2A but works very differently. The main differences:
| Topic | e-PW2A (OTM) | e-PW2B (LTM) |
|---|---|---|
| Who can tender | Any eligible contractor | Contractors enlisted with the PE |
| How price is quoted | Unit rate per BoQ item | One percentage, within ±5% of the official estimate |
| Low-price check | SLT formula | Outside ±5% is rejected; no SLT |
| Tie for lowest | Past performance | e-Lottery in e-GP |
| Experience and turnover | Required | Not required |
| Joint venture | Allowed from Tk. 3 crore | Not allowed |
| Subcontracting | Up to 30% | Not allowed |
If your PE keeps no enlistment list, TDS 5.1 lets you use the enlisted contractors of another reputable PE, or a list published by BPPA on its website.
02How the Document Works
e-PW2B has ten sections. Two of them must never be altered.
| Section | What it does | PE action |
|---|---|---|
| 1. ITT | Instructions to Tenderers: submission, evaluation and award rules. | Do not alter |
| 2. TDS | Tender Data Sheet: package-specific values, numbered like the ITT. | Fill in |
| 3. GCC | General Conditions of Contract. | Do not alter |
| 4. PCC | Particular Conditions: contract-specific values, numbered like the GCC. | Fill in |
| 5. Forms | Tender forms e-PW2B-1 to 5; contract forms 6 to 9. | Keep as issued |
| 6. BoQ | Items, quantities and the official cost estimate. | Prepare |
| 7–8. Specifications | General and Particular Specifications. | Prepare |
| 9. ES Specifications | Environmental, social, health and safety requirements. | Prepare |
| 10. Drawings | Dated, numbered drawings with revision numbers. | Attach |
| Form or format | Title |
|---|---|
| e-PW2B-1 | e-Tender Submission Letter |
| e-PW2B-2 | Tenderer Information (with beneficial ownership) |
| e-PW2B-3 | Personnel Information |
| e-PW2B-4 | Bank Guarantee for Tender Security |
| e-PW2B-5 | Bank's Letter of Commitment for Line of Credit |
| e-PW2B-6 to 9 | Notification of Award, Contract Agreement, Performance Security guarantee, Contract Amendment |
| Formats A to E | IFT, reporting the award, reporting contract signing, commencement letter, completion certificate |
03Key Time Limits
| Step | Time limit | Clause |
|---|---|---|
| Answer a clarification request | Within 5 working days, through e-GP | ITT 7.3 |
| Upload pre-tender meeting minutes | Within 5 working days | ITT 8.3 |
| Circulate an addendum | Within 5 working days of issue | ITT 9.2 |
| Extend after a late addendum | At least 3 working days if under one-third of preparation time remains | ITT 9.5 |
| Document fee paid | No later than the day before the deadline | ITT 19.1 |
| Tenderer answers a TEC clarification | At least 3 working days allowed | ITT 42.4 |
| Notice of rejecting all tenders | Within 3 working days of HOPE's decision | ITT 52.1 |
| Issue the NOA | Within 3 working days of approval, before validity expires | ITT 54.1 |
| Publish the award | Within 24 hours of the NOA, displayed 28 days | ITT 55.1 |
| Performance security furnished | Within 7 working days of the NOA (Rule 123(7)) | TDS 57.2 |
| Contract signed | Within 14 days of the NOA | TDS 61.2 |
| Publish contract signing | Within 3 days, displayed at least 30 days | ITT 62.1 |
| Hand over the site | Normally within 28 days of signing | PCC 12.1 |
| Pay a certified bill | Within 28 days of the certificate | GCC 53.1 |
| Take over completed works | Within 7 days of the PM's recommendation | GCC 61.1 |
| Certify the final account | Within 56 days of receiving it | GCC 63.2 |
04Enlistment and Qualification
Enlistment does most of the screening. Qualification on top of it is pass/fail and limited to three things you set in the TDS.
| Criterion | Clause | What to set |
|---|---|---|
| Enlistment | ITT 5.1, TDS 5.1 | Name the PE whose enlistment list applies. |
| Experience | ITT 11.1 | None. Tenderers are not required to have past experience. |
| Liquid asset | TDS 12.1 | An amount, usually 2–6 months of payment flow. |
| Key personnel | TDS 13.1 | Positions and total works experience in years. |
| Equipment | TDS 14.1 | Type, characteristics and minimum number, owned or with proven access. |
Liquid asset = (T ÷ N) × E E = official cost estimate, T = months between interim bills (usually 2–3), N = construction months
Example: the STD's Tk. 4 crore, 12-month contract With 1 month of work, 0.25 month to invoice, 0.25 month to certify and 0.5 month contingency, T is 2 months. Liquid asset = (2 ÷ 12) × 4 = about Tk. 0.66 crore.
- For a package of several lots, state the liquid asset, personnel and equipment for each lot. A tenderer bidding for several lots must meet the total of the lots it wants.
- No joint venture is permitted (ITT 15.1); a JV tender is non-responsive.
- No subcontracting of any part of the works (ITT 16.1, GCC 19.1). Doing so is a fundamental breach.
- The contractor must be a Bangladeshi national (GCC 9.1).
05Fill In the TDS
| TDS | What to insert |
|---|---|
| 1.1, 3.1 | PE name, tender name, reference, lot numbers (matching the BoQ) and source of funds. |
| 5.1 | The PE whose updated, valid enlistment makes a contractor eligible. |
| 12.1–14.1 | Liquid asset, key personnel and equipment, per lot where relevant. |
| 21.1(f) | The income-tax assessment year for the return acknowledgement. |
| 21.1(h) | Any additional documents, or "None". |
| 26.1 | Tender validity, normally 60 to 150 days. |
| 28.1 | Tender security as a fixed amount, not more than 3% of the official estimate, and the beneficiary. |
| 56.1 | Performance security: not required up to Tk. 1 crore; 5% of contract price above Tk. 1 crore. Delete the option that does not apply. |
| 57.2 | Performance security within 7 working days of the NOA (fixed text). |
| 60.1 | Retention per IPC: 10% up to Tk. 1 crore, 5% above Tk. 1 crore. |
| 61.2 | Contract signed within 14 days of the NOA (fixed text). |
| 64.1 | Proposed Adjudicator, hourly fee, reimbursable limits and biodata. |
Example: securities at two contract sizes On a Tk. 1.2 crore estimate, tender security can be up to Tk. 3.6 lakh. A Tk. 80 lakh contract needs no performance security and has 10% retention; a Tk. 1.2 crore contract needs a Tk. 6 lakh performance security and has 5% retention.
06Fill In the PCC
| PCC | What to insert |
|---|---|
| 1.1 | Contractor, PE, Project Manager, site location and drawing numbers, scope of works, original contract price (as in the NOA), intended completion date. |
| 1.1(oo), 31.1 | Commencement date, and a Start Date usually 14–21 days after it. |
| 2.5 | Sectional completion dates, if any. |
| 3.1, 53.3 | Addresses for notices and the contractor's bank account, confirmed by the bank and authenticated by the PE. |
| 6.1(k), 9.2 | Other contract documents (equipment schedule, site investigation reports) and any barred countries of origin. |
| 12.1 | Site possession date(s), normally within 28 days of signing. |
| 18.1, 20.1 | Key personnel, and who decides contractual matters if not the Project Manager. |
| 33.1–33.3 | Programme due (usually 15 days after signing), update interval, and Tk. 10,000–15,000 withheld for a late update. |
| 45.1 | Defects Liability Period, usually 12 months to cover a monsoon. |
| 54.1(i) | Additional compensation events, or "none". |
| 56.1 | Retention: 10% up to Tk. 1 crore, 5% above (same as TDS 60.1). |
| 57.1 | Liquidated damages 0.03–0.05% of contract value per day, capped at ≤ 10%. |
| 64.1, 64.2 | Whether as-built drawings are needed, the date, and the amount withheld if late. |
| 74.1 | Compensation for uncompleted works on default termination: 15–25% of the revised estimate. |
| 77.2(b), 77.3(b) | Adjudicator (appointing authority: President of IEB) and arbitration venue. |
07Official Estimate, BoQ and Specifications
In e-PW2B the BoQ carries the official cost estimate, and every tender is a percentage of it. A wrong estimate cannot be fixed by competition: if it is too high you overpay, if it is too low no one can tender within the band.
- Group items into sections (100 General, 200 Preliminary, 300 Main, 400 Other, 500 Misc.) where method, location, timing or cost differ.
- Compute quantities net from the drawings, in metric units, with no allowance for bulking, shrinkage or waste. Avoid spurious accuracy.
- Price each item with current rates including profit, overhead, VAT and incidental charges, so the grand total is a realistic estimate.
- Include a Dayworks schedule only when unforeseen work is likely, with nominal quantities.
- Add provisional sums in the summary for physical contingencies or price increases if needed.
- Write specifications for the widest competition, using recognised national standards and accepting equal or higher alternatives. Materials must be new and current.
- Prepare the ES Specifications from the environmental and social assessment (OHS, community safety, dust, waste, traffic, grievance mechanism, code of conduct), referring to BNBC 2020 where relevant.
Remove the BoQ, specification and drawing guidance notes before publishing; the STD says they must not appear in the final document.
08Clarifications and Addenda
- Clarification requests come through e-GP within the IFT time; answer within 5 working days. Requests after that date need not be answered.
- A pre-tender meeting, if stated in the IFT, is online. Upload minutes within 5 working days. Missing it does not disqualify anyone.
- Change the document only by a dated, numbered addendum, never by meeting minutes. Circulate it within 5 working days and post it where the IFT was posted.
- If less than one-third of the preparation time remains, extend the deadline by at least 3 working days.
09Opening and Responsiveness
- e-GP opens tenders automatically after the deadline and generates the Tender Opening Report.
- The TEC reviews the system-generated evaluation reports in four steps: preliminary, technical, financial and post-qualification.
- Preliminary: reject any tender missing duly e-signed forms, the letter of enlistment with the specified PE, the priced BoQ or a valid tender security.
- Technical: judge responsiveness on the tender alone, and check the adequacy and authenticity of the liquid asset, personnel and equipment evidence. A non-responsive tender cannot later be corrected.
- Ask for clarification through e-GP, by the TEC Chairperson only, allowing at least 3 working days. It cannot be used to make a tender responsive.
There is no minimum number of responsive tenders (ITT 41.3), e-GP has no arithmetic-correction step (ITT 44.1), and no negotiation is allowed with any tenderer (ITT 48.1).
10The ±5% Band and e-Lottery
- Each tenderer quotes only a percentage above, below or at par with the total official estimate, in the BoQ Offer Form. e-GP generates the offered figure and words.
- Any offer more than 5% above or below the official estimate is rejected (ITT 23.3 and 39.4). There is no SLT formula.
- Compare the remaining responsive tenders; the lowest evaluated price wins, subject to post-qualification.
- If two or more tie for lowest, run an open e-Lottery through e-GP. It can be run up to three times, ranking a second and third successful tenderer in case the first refuses or fails to sign.
Example: six offers on a Tk. 2 crore estimate The band is Tk. 1.90 to 2.10 crore. Offers of −6% and +7% are rejected. Three tenderers at −5% tie at Tk. 1.90 crore, ahead of −3% and +2%. The e-lottery ranks the three at −5%, and the first drawn is post-qualified.
For multiple lots, award each lot to one tenderer using the same method, choosing the combination of lowest evaluated tenders the tenderers have resources to perform.
11Post-qualification and Award
- Post-qualify the selected tenderer only against ITT 10–14 and its documents. If it fails, move to the next lowest evaluated tenderer.
- Issue the NOA (Form e-PW2B-6) within 3 working days of approval, with the draft contract, performance security amount and deadlines. The NOA forms the contract until signing.
- Publish the award (Format B) within 24 hours on the notice board or website and the BPPA website, for at least 28 days.
- Receive any performance security within 7 working days and verify it with the issuing bank; sign within 14 days.
- Publish contract signing (Format C), with beneficial ownership for contracts above Tk. 10 lakh, within 3 days, for at least 30 days.
- If the winner fails to furnish security or sign, annul the award, forfeit its tender security and award to the next lowest evaluated qualified tenderer.
- Return non-responsive tender securities after the evaluation report is approved, within 28 days of validity expiry; keep the 1st to 3rd lowest until the winner furnishes security and signs.
- Reject all tenders only on ITT 51.2 grounds with HOPE's approval, and not if the lowest price matches the market.
12Site, Commencement and Programme
- Hand over the site on the PCC date. Late possession is a compensation event; failing to hand over the full or a substantial part within 84 days of signing lets the contractor terminate.
- Issue the commencement letter (Format D) once the contract is signed and the site handed over; the contractor starts by the Start Date.
- Approve the Programme of Works and its updates; withhold the PCC amount while an update is overdue.
- Inspect and test regularly. No work may be covered without the PM's approval. Unspecified tests are at the contractor's cost only if they reveal a defect.
- The contractor must execute every BoQ item; skipping one without consent may be a fundamental breach.
13Variations and Extensions
| Change | Who approves |
|---|---|
| Variation up to 10% | Approving Authority of the original contract |
| Variation over 10% up to 30% | The next higher authority |
| Variation over 30% | Not allowed |
| Extension up to 30% of contract time | PE, on the PM's recommendation |
| Extension 30% to 100% | HOPE or an authorised officer |
| Extension over 100% | Secretary of the ministry or division |
- The contractor must notify a variation within 7 working days of becoming aware, or lose the claim. The PM prepares the order with plans, justification, itemised estimates and rates.
- If an item's quantity rises by more than 25% and that alone raises the contract price by more than 1%, agree an adjusted rate for the quantity beyond the BoQ.
- Price new items from the contractor's direct-cost breakdown plus its tender mark-up, or agreed market prices.
- If variations move the contract price by more than 20%, the performance security can be increased (or, with consent, reduced) in proportion.
- The PM decides an extension within 21 days of full information; delay caused by the contractor's failure to give early warning is not counted.
Example: a Tk. 1.2 crore contract Variations up to Tk. 12 lakh go to the original Approving Authority, Tk. 12–36 lakh to the next higher authority, and nothing beyond Tk. 36 lakh. On a 10-month contract, the PE can extend up to 3 months; up to 10 months needs HOPE.
14Payment, Retention and Damages
- The contractor submits monthly statements; the PM certifies the value of work executed at BoQ rates (including approved variations, dayworks and compensation events).
- Pay within 28 days of the certificate into the nominated account. Variation work is paid only after the variation is approved.
- Return retention after the Defects Liability Period, once the Defects Correction Certificate is issued.
- Adjust the price for changes in law after 28 days before the deadline, and for tax-rate changes with HOPE's approval.
Liquidated damages T = V × P × n (contract value × daily rate × days late)
Example: liquidated damages A Tk. 1.2 crore contract at 0.05% per day finishing 20 days late: 1,20,00,000 × 0.0005 × 20 = Tk. 1,20,000. With a 10% cap (Tk. 12 lakh), the cap is reached after 200 days, at which point delay becomes a fundamental breach.
15Completion, Termination and Disputes
- Take over within 7 days of the PM's completion recommendation and issue the completion certificate (Format E).
- The contractor submits the final account; certify it within 56 days or issue a Defects Liability Schedule.
- For a default, send a Notice to Correct first (reply within 5 days). For a fundamental breach, issue a Notice of Default with 21 days to explain, then a final notice with HOPE's approval. HOPE may form a Contract Termination Review Committee.
- On default termination, jointly measure the work (7 days' notice), certify its value and deduct the PCC compensation (15–25% of the revised estimate of uncompleted works).
- Termination for convenience needs 21 days' notice and may not be used to give the work to someone else.
- Disputes: amicable settlement, then the Adjudicator (referral within 14 days, decision within 28 days), then arbitration under the Arbitration Act 2001.
16Publishing Checklist
- Estimate is within Tk. 5 crore, the package is not split, and LTM conditions apply.
- The enlistment list in TDS 5.1 is named and up to date.
- ITT and GCC are untouched; every TDS and PCC blank is filled.
- Official cost estimate checked against current rates: tenderers can only move 5% either way.
- Liquid asset derived from the estimate and period; personnel and equipment set per lot.
- Tender security is a fixed amount ≤ 3% of the estimate.
- Performance security and retention match the contract-size rules, and TDS 60.1 agrees with PCC 56.1.
- BoQ complete, quantities net from drawings; guidance notes removed.
- General, Particular and ES Specifications and drawing list are attached.
- Validity period, assessment year, LD rate and cap, DLP and Adjudicator are set.
Bidorix can review your official estimate, TDS, PCC and BoQ before you publish.
17Common Questions
Can a contractor not enlisted with us tender?
No. The invitation is limited to contractors with updated, valid enlistment under the PE named in TDS 5.1. A tender without the letter of enlistment is rejected at the preliminary check.
Do we run the SLT check in e-PW2B?
No. Offers more than 5% above or below the official estimate are rejected outright; anything within the band is compared on price.
Several tenderers quoted the same lowest percentage. What now?
Select by open e-Lottery in e-GP. It can be run up to three times so that a second and third tenderer are ready if the first refuses or fails to sign.
Can we ask for past experience to keep weak contractors out?
No. ITT 11.1 says tenderers shall not be required to have past experience. Use the liquid asset, personnel and equipment criteria, and your enlistment rules.
Can a variation take the contract above the original price by 35%?
No. Variation orders over 30% of the original contract price cannot be approved by any authority.