Procurement of 200mm uPVC Pipe and Fittings (For 1 cusec Buried Pipe Irrigation Channel)
Procurement of 200mm uPVC Pipe and Fittings (For 1 cusec Buried Pipe Irrigation Channel)
Procurement summary
- Procuring entity
- Project Director Office Ashuganj-Palash Green Project
- Organization
- bangladesh agricultural development corporation (badc)
- Ministry
- ministry of agriculture
- Location
- Brahmanbaria, Brahmanbaria
- Procurement nature
- Goods
- Procurement type
- NCT
- Procurement method
- Open Tendering Method (OTM)
- Lot
- e-GP/APGP/2026-27/GD-06/Lot-02
- Package no.
- e-GP/APGP/2026-27/GD-06/Lot-02
- APP ID
- 230673
- Invitation reference no.
- e-GP/APGP/2026-27/GD-06/Lot-02/T-02
Key dates
- Published
- 14 September 2026
- Document last selling date
- 29 September 2026
- Pre-tender meeting
- 14 September 2026
- Tender security submission deadline
- 29 September 2026
- Opening date
- 29 September 2026
- Closing date
- 29 September 2026
Costs and securities
- Estimated cost (APP)
- BDT 2,13,00,000
- Document price
- BDT 4,000
- Tender security
- BDT 4,26,000
Funding
- Project
- Ashuganj-Palash Green Project
- Budget type
- Development
- Source of funds
- Government
Eligibility criteria
Only local manufacturer who have industrial license of producing uPVC materials will be allowed to bid this tender. Updated ISO standardization certificate of the Manufacturer must be submitted with the offer. Manufacturer must have industrial Project registration license issued by the Board of investment Government of Bangladesh. Five years over all Manufacturer experience certificate of those particular/respective materials enclosed with the offer. The satisfactory completion of similar nature of goods (Supply of 200 mm uPVC Pipe & Fittings) with a minimum of Tk. 170.00 (One Hundred Seventy) Lakh only under a single contract in the last 05 (five) years. The minimum amount of liquid assets i.e. working capital or credit line(s), net of other contractual commitments is Tk.160.00 One Hundred Sixty) Lakh at least in a single day not before 14-09-2026. Tenderers who supplied uPVC materials at any office of BADC and did not correct the defects in time within the defect’s liability period…